December 14, 2023
From HallCWiki
Contents
RC Meeting Information
RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)
- Zoom remote connection information: https://logbooks.jlab.org/entry/4229331
- RC meeting today
Useful Links
Current Run Plan
- Continue run plan: https://hallcweb.jlab.org/wiki/index.php/Short_Term_Run-Plan
- cycle KinC_x60_2 then KinC_x60_2'
- Only need four 1-hour production runs on LD2 for each cycle of each setting.
- Beam off 7:00 am Friday 15 Dec
Notices in Effect for Shift Crew
- All shifts should come in as planned.
- cc Heidi & Steve Lassiter on any cryo logbook entry (fansler@jlab.org, lassiter@jlab.org)
- Physically verify green led of gas flow and BCM temps in electronics room
- Record HMS (electron) tracking efficiency from each 50K replay report
Current Issues
- No beam because of cryo issue - should come back mid day shift
- On call list seems incomplete and should be addressed by the Hall: https://logbooks.jlab.org/entry/4230495
- We need other indications of this interlock. In Hall A, we have it shut off detector HV via the alarm handler, and we have a flow rate alarm. Seems the useful PV values have not been working since 1-Sept.
- Need alarm on NPS Sweep (or improved visual display of status).
- NPS PMT/Base failures are propagating into columns 12, 13
Planned Access to the Hall
Planned Accelerator Configuration Changes
- We will run until 07:00 Dec 15.
- Target will be warmed up and parked.
- Hall will remain in Controlled Access until 07:00 Dec 19
- Beam studies (Day Shift) Dec 19 will send beam into hall
- Hall will return to Controlled Access at 16:00 on Dec 19
Special Requests
- Shutdown repair plan
- Remove columns 0-19, start restoration at column 19
- Best option for radiation damage.
- Either extend shutdown beyond Jan 20 to restore all columns
- Or: only restore colulmns 4-19
- Remove columns 0-19, start restoration at column 19
- NPS Shutdown Checklist for Dec 22-Jan 2 SAD?
- Turn off HMS magnets (Dec 15)
- Turn off HMS detector HV (Dec 15)
- Dec 22
- Turn off NPS HV
- Turn off NPS LV
- Turn off NPS Chiller
- Turn off VLD (LED controller)