Hall C Weekly Meeting - April 28, 2014

From HallCWiki
Jump to: navigation, search
  • Walter Kellner
    • Cleaning up in preparation for power washing and filling the SOS ruts in the floor. Also cleaning
    • for delivery of SHMS magnet steel and the open house
    • Helped with getting HMS Q2 ready to cool down
    • Welded caps on G0 lines so they can be stored outside
    • Gas system work in the gas shed is done
  • Bert Metzger
    • All but a few panels of the SHMS electronics room floor are installed.
    • Shielding in the detector hut should start this week.
  • Mike Fowler
    • The HMS dipole is full of LHe and Q3 is at 117K and cooling down at 0.6K/hour.
  • Joe Beaufait
    • Material for the SHMS electrical install is arriving
    • The non-functioning Moller SC solenoid power supply has been found. Joe will diagnose and try to repair the supply. The suspicion is that it is simply a bad Klixon
  • Paul Brindza
    • SHMS
      • Assembly of the HB LHe Vessel at MSU is continuing
      • The Q1 LN2 shield is being assembled at SMI
      • At SigmaPhi, the Vacuum Impregnation (VPI) of coil #1 went well. The mold is being disassembled.
      • The winding of the first layer of coil #2 was complete today
      • SigmaPhi started two shift winding
    • Three Moller coils arrived last week. Four are now in house. 3 look OK and the fourth is questionable. Advice is being sought from an outside expert.
    • The SHMS stell will be delivered this week. (Weather permitting)
  • Bert Manzlak
    • A worker slipped and fell while wearing a booty in the Hall B clean room. The fall required only first aid and was reported to medical services.