==Log Entries==
 
==Log Entries==
** Nov. 26th Kepcos replaced Agilents  https://logbooks.jlab.org/entry/3744320
+
* Nov. 26th Kepcos replaced Agilents  https://logbooks.jlab.org/entry/3744320
** Dec. 26th V_in vs Current Calibration for two Kepcos in voltage control mode https://logbooks.jlab.org/entry/3747508
+
* Dec. 26th V_in vs Current Calibration for two Kepcos in voltage control mode https://logbooks.jlab.org/entry/3747508
** Jan. 4th Swapped out Kepco with another Kepco because it was not stable https://logbooks.jlab.org/entry/3758511
+
* Jan. 4th Swapped out Kepco with another Kepco because it was not stable https://logbooks.jlab.org/entry/3758511
** Jan. 15th Swapped out Kepco with another Kepco because it was running hot and tripping https://logbooks.jlab.org/entry/3764365
+
* Jan. 15th Swapped out Kepco with another Kepco because it was running hot and tripping https://logbooks.jlab.org/entry/3764365
** Feb. 9th Field sweep program updated for Agilent https://logbooks.jlab.org/entry/3780264
+
* Feb. 9th Field sweep program updated for Agilent https://logbooks.jlab.org/entry/3780264
** Feb. 10th Replaced Kepco with Agilent.  Rearranged rack for better cooling https://logbooks.jlab.org/entry/3781492
+
* Feb. 10th Replaced Kepco with Agilent.  Rearranged rack for better cooling https://logbooks.jlab.org/entry/3781492
** Feb. 14th Replaced Agilent with new Kepco.  In constant current mode the inductive load option interfered with NMR https://logbooks.jlab.org/entry/3783977
+
* Feb. 14th Replaced Agilent with new Kepco.  In constant current mode the inductive load option interfered with NMR https://logbooks.jlab.org/entry/3783977
** March 18th In constant voltage mode, coils need time to warm up https://logbooks.jlab.org/entry/3805990
+
* March 18th In constant voltage mode, coils need time to warm up https://logbooks.jlab.org/entry/3805990
** March 22nd New kepco had odd behavior in voltage mode.  Transverse NMR was not working.  Left in current mode. https://logbooks.jlab.org/entry/3807357
+
* March 22nd New Kepco had odd behavior in voltage mode.  Transverse NMR was not working.  Left in current mode. https://logbooks.jlab.org/entry/3807357
** March 22nd Odd behavior explained from above.  Noticed possible grounding issues.  https://logbooks.jlab.org/entry/3807894
+
* March 22nd Odd behavior explained from above.  Noticed possible grounding issues.  https://logbooks.jlab.org/entry/3807894
** March 24th Trouble getting transverse NMR signal.  Bad Cable?  https://logbooks.jlab.org/entry/3809148
+
* March 24th Trouble getting transverse NMR signal.  Bad Cable?  https://logbooks.jlab.org/entry/3809148
  
==Coil Currents for D2n==
+
==Coil Currents==
 +
[[ Image:D2nCoilCurrent.png |600px |Coil Currents for D2n]]
  
 
==Labview Program Guide==
 
==Labview Program Guide==
  
 
==Field Measurements==
 
==Field Measurements==
 +
*; A1n Vertical Field Measurement (March 13th, 2019)
 +
https://logbooks.jlab.org/entry/3804362
  
 
==Plan for returning from COVID shutdown==
 
==Plan for returning from COVID shutdown==
** Follow manufactureres "Check out" procedure for new power supply which was delivered during shutdown
+
* Work that can begin immediately (June 10th, 2020) Task 1 in HCLIST (http://devweb.acc.jlab.org/CSUEApps/hclist/atlis.php?load=Task&task_id=1818)
** Measure resistance to ground for both coils
+
** Follow manufacturers "Check out" procedure for new power supply which was delivered during shutdown
** Install latest new power supply, add additional circuitry
+
*** This can be done anywhere, I just need some connectors from Ethan or Jack.  Currently the new power supply is in Bill's office.
 +
** Measure resistance to ground for both coils
 +
** Install latest new power supply, add additional circuitry (RLC).
 
** Test power supplies in both current and voltage control mode
 
** Test power supplies in both current and voltage control mode
** Look at PS output on scope, with and without RF on.
+
*** MUST check PS output on scope, with and without RF on.
 +
*** LIKE to check PS output on scope, with and without sense wires attached.
 +
*** LIKE to check PS output on scope, with and without additional circuity (RLC).
 +
**LABVIEW
 +
*** Determine calibrations: Current to field, field direction equation for epics, function generator output vs PS output, ... 
 +
*** Update programs.  One for voltage mode, one for current mode
 +
 
 +
 
 +
*After the cell is polarized  (Task 9 in HCLIST)
 
** Test NMR in both voltage and current mode
 
** Test NMR in both voltage and current mode
** Ensure Labview is ready to go for either configuration
 
  
 
==Manuals/Documentation==
 
==Manuals/Documentation==
 
* [[Media:KEPCO.pdf|Note on KEPCO power supplies]]
 
* [[Media:KEPCO.pdf|Note on KEPCO power supplies]]

Latest revision as of 11:37, 15 June 2020

This page is dedicated to all things Target Field related

Log Entries

Coil Currents

Coil Currents for D2n

Labview Program Guide

Field Measurements

  • A1n Vertical Field Measurement (March 13th, 2019)

https://logbooks.jlab.org/entry/3804362

Plan for returning from COVID shutdown

  • Work that can begin immediately (June 10th, 2020) Task 1 in HCLIST (http://devweb.acc.jlab.org/CSUEApps/hclist/atlis.php?load=Task&task_id=1818)
    • Follow manufacturers "Check out" procedure for new power supply which was delivered during shutdown
      • This can be done anywhere, I just need some connectors from Ethan or Jack. Currently the new power supply is in Bill's office.
    • Measure resistance to ground for both coils.
    • Install latest new power supply, add additional circuitry (RLC).
    • Test power supplies in both current and voltage control mode
      • MUST check PS output on scope, with and without RF on.
      • LIKE to check PS output on scope, with and without sense wires attached.
      • LIKE to check PS output on scope, with and without additional circuity (RLC).
    • LABVIEW
      • Determine calibrations: Current to field, field direction equation for epics, function generator output vs PS output, ...
      • Update programs. One for voltage mode, one for current mode


  • After the cell is polarized (Task 9 in HCLIST)
    • Test NMR in both voltage and current mode