= HMS/SHMS Magnet Cycling Procedures =
+
=[[Hall C One pass commissioning plan | Beam energy of 2.2 GeV ]]=
  
=== HMS ===
+
= Beam energy of 6.4 GeV =
* Set DIPOLE by NMR coming DOWN 200 A above.
+
== Initial conditions ==  
* Set QUADS by initially setting to a current of 200 A above the set currents (or the maximum current of 1100 A for Q1 if set current + 200 > 1100), and then coming DOWN.
 
*See [[How-to#Magnets|instructions and limits]] (do not exceed these limits!!!)
 
 
 
=== SHMS ===
 
* General principal:  A magnet will be “on loop” if it has been taken to Imax (11 GeV) and stays on the descending branch of the hysteresis loop. Otherwise it is "off loop"
 
* Cycle procedure: Go to Imax and descend to target current.
 
*See [[How-to#Magnets|instructions and limits]] (do not exceed these limits!!!)
 
* Action logic table
 
{| border="1" cellpadding="2" valign="top" style="text-align: center;"
 
|  Status/Action
 
| Magnet status is “on loop”
 
| Magnet status is “off loop”
 
|-
 
| Increasing abs(p) at this polarity
 
| Cycle
 
| Cycle
 
|-
 
| Decreasing abs(p) at this polarity
 
|  Descend to target current
 
|  Cycle
 
|-
 
|Changing polarity
 
| Set to 0 current, switch polarity, cycle
 
| Set to 0 current, switch polarity, cycle
 
|}
 
 
 
= Beam energy of 2.2 GeV =
 
 
 
== Initial conditions ==
 
* HMS/SHMS angle surveys.
 
* Beamline BPM and Harp surveys. Check offsets in MCC database.
 
 
* HMS/SHMS Conditions:  
 
* HMS/SHMS Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
Line 41: Line 10:
 
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  |-
 
  |-
  ! HMS angle/momentum  || 25 deg, -1.6 GeV/c
+
  ! HMS angle/momentum  || 15 deg, -3.0 GeV/c
 
  |-
 
  |-
  ! SHMS angle/momentum  || 25 deg, -1.6 GeV/c
+
  ! SHMS angle/momentum  || 15 deg, -3.0 GeV/c
 
  |}
 
  |}
* Run 2.2 GeV beam four 4 days and switch to 3 pass.
 
* Run 6.4 GeV beam  and switch to 5 pass.
 
* Run 10.6 GeV beam.
 
  
== Beam Checkout with Superharps and Beam Position Monitors ==  
+
== Beam Checkout with Superharps and Beam Position Monitors (3 hours) ==
 
* Experts: Mark Jones, Deb Biswas, Thir Guatam
 
* Experts: Mark Jones, Deb Biswas, Thir Guatam
 
* Expected time: 3 hours
 
* Expected time: 3 hours
Line 63: Line 29:
 
  |}
 
  |}
 
*Runplan: [https://github.com/MarkKJones/fall2017-plans/blob/master/beam-checkout-superharps-bpms/beam-checkout-superharps-bpms.pdf pdf file]
 
*Runplan: [https://github.com/MarkKJones/fall2017-plans/blob/master/beam-checkout-superharps-bpms/beam-checkout-superharps-bpms.pdf pdf file]
 +
* Ask MCC to do superharp scan with superharps IHA3H07A and IHA3H07B and put entry in ELOG. Record the 3 BPMs positions (3H07A,3H07B,3H07C) during scan.
 +
** Want beam spot  with  sigma_x and sigma_y below 200 um ( beam pass 1-4) and below 300 um for beam pass 5.
 +
* Verify Girder BPM position to Harp positions.
  
== Center beam  on C-hole target ==
+
== Center beam  on C-hole target ( 1 hour)==
 
* Experts:  
 
* Experts:  
 
* Expected time: 1 hour
 
* Expected time: 1 hour
Line 81: Line 50:
 
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  |-
 
  |-
  ! HMS angle/momentum  || 25 deg, -1.6 GeV/c
+
  ! HMS angle/momentum  || 15 deg, -3.0 GeV/c
 
  |-
 
  |-
  ! SHMS angle/momentum  || 25 deg, -1.6 GeV/c
+
  ! SHMS angle/momentum  || 15 deg, -3.0 GeV/c
 
  |}
 
  |}
 
* Run plan: [https://hallcweb.jlab.org/wiki/index.php/Beam_Checkout_Procedures  Procedure]
 
* Run plan: [https://hallcweb.jlab.org/wiki/index.php/Beam_Checkout_Procedures  Procedure]
 +
* Once hole is found, take 20 minutes run at 20uA for good statistics
  
== Initial HMS/SHMS Detector Checkout ==
+
== Detailed Detector Checkout ( 2 hour)==
* SHMS/HMS optics experts:
+
* Experts:  
* HMS DC experts:  
+
* Expected time: 2 hour
* Expected time: 1 hour
+
* Prerequisite: Eric Pooser will do invasive checkout of HMS/SHMS trigger with beam.
* Goal: Initial checkout of the HMS/SHMS detectors. Working well enough for carbon elastics data and initial checkout of the SHMS/HMS tunes.
 
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || 20 μA
 
  |-
 
  |-
 
  ! fast raster: || off
 
  ! fast raster: || off
Line 105: Line 74:
 
  ! HMS/SHMS trigger: || SCIN 3/4,SCIN 3/4
 
  ! HMS/SHMS trigger: || SCIN 3/4,SCIN 3/4
 
  |-
 
  |-
  ! HMS angle/momentum  || 25 deg, -1.6 GeV/c
+
  ! HMS angle/momentum  || 15 deg, -3.0 GeV/c
 
  |-
 
  |-
  ! SHMS angle/momentum  || 25 deg, -1.6 GeV/c
+
  ! SHMS angle/momentum  || 15 deg, -3.0 GeV/c
 
  |}
 
  |}
* General Run Plan:
+
=== Trigger ===
* [https://github.com/MarkKJones/fall2017-plans/blob/master/initial-hms-shms-detector-checkout/hms_25deg_16gev_fp.pdf HMS focal plane plots]
+
*Set HMS/SHMS trigger threshold for PID trigger section to 10 mV.  
* [https://github.com/MarkKJones/fall2017-plans/blob/master/initial-hms-shms-detector-checkout/shms_25deg_16gev_fp.pdf SHMS focal plane plots]
+
*Software cuts can be placed on trigger ADC data to study efficiencies.
* [https://github.com/MarkKJones/fall2017-plans/blob/master/initial-hms-shms-detector-checkout/hms_25deg_16gev_kin.pdf HMS physics plots]
 
* [https://github.com/MarkKJones/fall2017-plans/blob/master/initial-hms-shms-detector-checkout/shms_25deg_16gev_kin.pdf SHMS physics plots]
 
* Need to have rough calibration of BCM1 and BCM2.
 
* First check trigger rates ( SHMS/HMS expects 4kHz/5kHz good electrons at 20uA and )
 
* Check background triggers rate
 
* Confirm the HMS DC tracking is working properly and efficiency is high.
 
* Compare HMS/SHMS focal plane plots to MC simulation.
 
=== Wire Chamber ===
 
* SHMS Run plan:
 
* HMS Run plan:
 
  
=== Shower Counter ===
+
=== Cerenkov ===
* SHMS Run plan: [https://github.com/MarkKJones/fall2017-plans/tree/master/shms-calo-commissioning files]
+
* SHMS Noble Gas Run Plan: Scan of HV ( Eric Pooser)
* HMS Run plan: [https://github.com/MarkKJones/fall2017-plans/tree/master/hms-calo-commissioning files]
+
Run 1 HV Settings: PMT1 = 2200 V, PMT2 = 2230 V, PMT3 = 2115, PMT4 = 2030
 +
Run 2 HV Settings: PMT1 = 2300 V, PMT2 = 2320 V, PMT3 = 2215, PMT4 = 2130
 +
** These are the spring 2017 KPP HV settings for reference:  NGC1 : 2255 V, NGC2 : 2280 V, NGC3 : 2165 V, NGC4 : 2087 V
 +
** We will also need to check the NGCER sum the PID trigger circuit to ensure that we are not saturating the FADC channel
  
=== Scintillator ===
+
*Run plan (series of 15 minutes runs)
* SHMS Run plan:
+
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
* HMS Run plan:
+
|-
 +
! Run  || HMS DAQ  || SHMS DAQ || Comments
 +
|-
 +
! 1    || No data taking  ||  Only 3/4 scin trigger || Checkout of HMS 3/4 trigger ; SHMS NGC HV NGC1 : 2255 V, NGC2 : 2280 V, NGC3 : 2165 V, NGC4 : 2087 V
 +
|-
 +
!  2 || Only 3/4 scin trigger || No data taking ||Checkout of SHMS 3/4 trigger
 +
  |-
 +
  ! 3  || Only 3/4 scin trigger ||  Only 3/4 scin trigger  || Checkout of HMS ELCLEAN/ELREAL trigger; SHMS NGC HV PMT1 = 2200 V, PMT2 = 2230 V, PMT3 = 2115, PMT4 = 2030
 +
|-
 +
! 4  || Only 3/4 scin trigger ||  Only 3/4 scin trigger || Checkout of HMS ELCLEAN/ELREAL trigger ; SHMS NGC HV PMT1 = 2300 V, PMT2 = 2320 V, PMT3 = 2215, PMT4 = 2130
 +
|-
 +
! 5  || Only ELCLEAN trigger ||  Only 3/4 scin trigger  || Checkout of SHMS ELCLEAN/ELREAL trigger
 +
|-
 +
! 6  || Only ELREAL trigger ||  Only 3/4 scin trigger  || Checkout of SHMS ELCLEAN/ELREAL trigger
 +
|-
 +
! 7  || ELREAL trigger, prescale 3/4 SCIN ||  Only ELCLEAN  ||
 +
|-
 +
! 8  || ELCLEAN trigger, prescale 3/4 SCIN ||  Only ELREAL ||
 +
|-
 +
! 9  || ELCLEAN trigger, different prescale 3/4 SCIN ||  ELREAL, prescale 3/4 scin ||
 +
|-
  
=== Cerenkov ===
+
|}
* SHMS Heavy Gas Cherenkov: [https://github.com/MarkKJones/fall2017-plans/blob/master/shms-hgcer-commissioning/shms-hgcer-commissioning-plan-2017.pdf Run Plan]
 
* HMS Run plan:
 
  
===Aerogel===
+
== Checkout of SHMS/HMS focal plane tune ( 1 hour)==
* SHMS Run plan:[https://github.com/MarkKJones/fall2017-plans/tree/master/shms-aero-commissioning Files]
+
* Experts:  
 
 
== Initial checkout of SHMS/HMS tune ==
 
* Experts: M Jones, H. Szumila
 
 
* Expected time: 1 hour
 
* Expected time: 1 hour
* Goal: Check tune with sieve
+
* Goal: Look at focal plane with sieve to check tune
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || 20 μA
 
  |-
 
  |-
 
  ! fast raster: || off
 
  ! fast raster: || off
Line 151: Line 128:
 
  ! target: || 0.5% carbon
 
  ! target: || 0.5% carbon
 
  |-
 
  |-
  ! HMS/SHMS collimator: || SIEVE , CENTERED SIEVE
+
  ! HMS/SHMS collimator: || SIEVE , Centered sieve
 
  |-
 
  |-
 
  ! HMS/SHMS trigger: || SCIN 3/4,SCIN 3/4
 
  ! HMS/SHMS trigger: || SCIN 3/4,SCIN 3/4
 
  |-
 
  |-
  ! HMS angle/momentum  || 25 deg, -1.6 GeV/c
+
  ! HMS angle/momentum  || 15 deg, -3.0 GeV/c
 
  |-
 
  |-
  ! SHMS angle/momentum  || 25 deg, -1.6 GeV/c
+
  ! SHMS angle/momentum  || 15 deg, -3.0 GeV/c
 
  |}
 
  |}
*Plots of focal plane for [https://github.com/MarkKJones/fall2017-plans/blob/master/initial-hms-shms-detector-checkout/hms_sieve_25deg_16gev_fp.pdf HMS focal plane] and [https://github.com/MarkKJones/fall2017-plans/blob/master/initial-hms-shms-detector-checkout/shms_sieve_25deg_16gev_fp.pdf SHMS focal plane]
 
*For SHMS use [https://hallcweb.jlab.org/wiki/images/c/c5/160512_jure_fp_patterns.pdf these plots] to help guide the setting of the quadrupoles.
 
*For HMS sieve, rate 340 Hz at 20uA
 
*For SHMS sieve, rate of 285 Hz at 20 uA
 
  
== Beam Energy Measurement ==
+
== Different Pi/e ratios ( 1.5 hour)==
* Experts: MCC,Mark Jones, Dave Mack
+
* Experts: SImona
* Expected time: 2 hours
+
* Expected time: 1.5 hr
* Goal: Measure beam energy for carbon elastics.
+
* Goal:  
 +
**Runs with different central momentum and different pi/e ratios.
 +
**Two runs with LH2 and one with LD2
 +
**Take each setting with only 3/4 scin trigger and for 30 minutes
 +
** Set PID tirgger thresholds to 10 mV. Offline will determine thresholds to test later.
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5uA
+
  ! beam current:  || 5-20 μA
 +
|-
 +
! fast raster: || 2x2mm
 +
|-
 +
! target: || 10cm LH2, 10cm LD2
 +
|-
 +
! HMS/SHMS collimator: || Pion/Collimator
 
  |-
 
  |-
  ! fast raster: || off
+
  ! HMS/SHMS trigger: || SCIN 3/4 /  SCIN 3/4
 
  |-
 
  |-
  ! target: || none
+
  ! SHMS/HMS angle/momentum  || 25. deg, -3.0 GeV/c, -1.4
 
  |}
 
  |}
*Run Plan: [http://opsntsrv.acc.jlab.org/ops_docs/online_document_files/MCC_online_files/HallC_energy_measure_proc.pdf MCC procedure]
+
* Run Plan
 
 
== HMS delta scan with LH2 ==
 
* Expected time: 5 hour
 
* Goal: Checkout HMS delta matrix. Have baseline for comparison at higher HMS central momentum 
 
* Conditions:
 
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 3 μA
+
  ! HMS angle/mom || SHMS angle/mom || Target || HMS/SHMS Trigger
|-
 
! fast raster: || 1x1cm
 
|-
 
  ! target: || 10cm LH2
 
 
  |-
 
  |-
  ! HMS collimator: || Pion
+
  ! 25./-3.0 || 25./-3.0 || 10cm LH2  || Only 3/4 scin
 
  |-
 
  |-
  ! HMS trigger: || SCIN 3/4
+
  ! 25./-1.4 || 25./-1.4 || 10cm LH2  || Only 3/4 scin
 
  |-
 
  |-
  ! HMS angle/momentum  || 13.5 deg, -2.309 to -1.889 GeV/c
+
  ! 25./-1.4 || 25./-1.4 || 10cm LD2  || Only 3/4 scin
 +
  |}
  
|}
+
== Defocused Tune for SHMS/HMS ( 1 hour)==
*HMS Run Plan:[https://github.com/MarkKJones/fall2017-plans/blob/master/HMS-delta-scan-hyd/HMS-elastic-carbon-run-plan.pdf pdf]
+
* Experts: Hamlet
 
+
* Expected time: 1 hr
== Fine tune SHMS with Carbon 4.4 inelastic  ==
+
* Goal: Have a wider y_fp to calibrate the calorimeter over regions that are not usually hit with the standard hourglass tune.
* Experts: M. Jones, H. Szumila
 
* Expected time: 1 hour
 
* Goal: Fine tune the SHMS quads and dipole with carbon 4.4 inelastic
 
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 3 μA
+
  ! beam current:  || 5-20 μA
 
  |-
 
  |-
  ! fast raster: || off
+
  ! fast raster: || 2x2mm
 
  |-
 
  |-
  ! target: || 0.5% carbon
+
  ! target: || 10cm LH2
 
  |-
 
  |-
  ! SHMS collimator: || CENTERED SIEVE
+
  ! HMS/SHMS collimator: || Pion/Collimator
 
  |-
 
  |-
  ! SHMS trigger: || SCIN 3/4
+
  ! HMS/SHMS trigger: || SCIN 3/4 /  SCIN 3/4
 
  |-
 
  |-
  ! SHMS angle/momentum  || 13.5 deg, -2.105 GeV/c
+
  ! SHMS/HMS angle/momentum  || 25. deg, -3.0 GeV/c, Q2 at 1.2 times normal
 
 
 
  |}
 
  |}
*SHMS Run Plan: [https://github.com/MarkKJones/fall2017-plans/blob/master/carbon-elastic/SHMS-elastic-carbon-run-plan.pdf pdf]
+
*Run Plan:[https://github.com/MarkKJones/fall2017-plans/tree/master/defocused-tune Documents]
  
== SHMS Delta checkout  with Carbon Elastic ground state ==
+
== Elastic p(ep) Checkout Small angle (2 hours) ==
* Experts: M. Jones, H. Smuzila
+
* Experts:  
* Expected time: 3 hour
+
* Expected time:  
* Goal: To take data with carbon elastic ground state and first excited state to test delta resolution.
+
* Goal:  
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || 10 μA
 +
|-
 +
! fast raster: || 1x1mm2
 
  |-
 
  |-
  ! fast raster: || off
+
  ! target: || 10cm LH2
 
  |-
 
  |-
  ! target: || 0.5% carbon
+
  ! HMS/SHMS collimator: || PION , COLLIMATOR
 
  |-
 
  |-
  ! SHMS collimator: || CENTERED SIEVE
+
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  |-
 
  |-
  ! SHMS trigger: || SCIN 3/4
+
  ! HMS angle/momentum  || 13.5/16. deg / 5.398/5.074 GeV
 
  |-
 
  |-
  ! SHMS angle/momentum  || 7.5 deg, 2.1 GeV/c
+
  ! SHMS angle/momentum  || 8.,10.,13.5 deg / 6.017,5.814,5.398 GeV
 
  |}
 
  |}
*Run Plan:
+
*Run plan
 +
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 +
|-
 +
! HMS Angle/Mom || HMS rate  || SHMS Angle/Mom  || SHMS rate  || Run time
 +
|-
 +
! 13.5/5.398    ||  300      ||  8./6.017      || 3300 Hz        || 15 minutes
 +
|-
 +
! 13.5/5.398    ||  300      ||  10./5.817      || 1000        || 30 minutes
 +
|-
 +
! 16.0/5.074    ||  100      ||  13.5/5.398      || 150        || 60 minutes
 +
|}
  
== SHMS/HMS Delta Matrix calibration  ==
+
== HMS/SHMS Angle and Position Matrix Optimization (5 hours)==
* Experts: M. Jones, H. Smuzila
+
* Experts:  
* Expected time: 12 hour
+
* Expected time: 5 hours.
* Goal: To
+
* Goal:  
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || 20 μA ( more is better)
 
  |-
 
  |-
 
  ! fast raster: || off
 
  ! fast raster: || off
 
  |-
 
  |-
  ! target: || 0.5% carbon
+
  ! target: || optics targets
 
  |-
 
  |-
  ! HMS/SHMS collimator: || Pion , Collimator
+
  ! HMS/SHMS collimator: || Sieve , Centered/Shifted Sieve
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! HMS/SHMS trigger: || 3/4 scin, 3/4 scin
 
  |-
 
  |-
  ! HMS angle/momentum  || 13.5 deg, various
+
  ! HMS angle/momentum  || 15 and 22. deg,  
 
  |-
 
  |-
  ! SHMS angle/momentum  || 13.5 deg, various
+
  ! SHMS angle/momentum  || 15. and 22. deg,
 
  |}
 
  |}
*Run Plan:
+
*Series of runs changing target.
*Try with different vertical and horizontal beam positions.
+
**SHMS has two sieves with the holes shifted in the horizontal.
 
+
**HMS has only one sieve which will always be used.
 
+
** No raster.  
== 1H(eep) Coincidence SHMS (proton) and HMS (electron) ==
+
** Time is assuming 20uA.
* Experts: D. Dutta, S. Basnet, A. Karki
 
* Expected time:  1 hour
 
* Goal: Setup coincidence timimg. Kinematic for HEEPcheck. Measure cross section.
 
* Conditions:
 
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current: || 5-60 μA
+
  ! Target || HMS angle || HMS momentum || SHMS angle || SHMS momentum  || SHMS collimator || Time
 
  |-
 
  |-
  ! fast raster: || 1x1mm
+
  ! 0,+/- 10cm || 15. deg ||  -4.0|| 15. deg ||  -4.0 || Centered Sieve || 30 min
 
  |-
 
  |-
  ! target: || 10cm LH2, 10cm dummy
+
  ! 0,+/- 10cm || 15. deg ||  -4.0|| 15. deg ||  -4.0 || Shifted Sieve || 30 min
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! +/- 5cm || 15. deg ||  -4.0|| 15. deg ||  -4.0 || Centered Sieve || 30 min
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! +/- 5cm || 15. deg ||  -4.0|| 15. deg ||  -4.0 || Shifted Sieve || 30 min
 
  |-
 
  |-
  ! HMS angle/momentum || 65.1 deg, -0.936 GeV/c
+
  ! 0,+/- 10cm || 22. deg || -3.2|| 22. deg ||  -3.2 || Centered Sieve || 1.5 hr
 
  |-
 
  |-
  ! SHMS angle/momentum || 25.0 deg, +2.012 GeV/c
+
  ! 0,+/- 10cm || 22. deg || -3.2|| 22. deg ||  -3.2 || Shifted Sieve || 1.5 hr
 
  |}
 
  |}
*Run Plan:
 
  
== 1H(eep) Coincidence SHMS (electron) and HMS (proton) ==
+
== Large Ytar: HMS/SHMS Angle and Position Matrix Optimization (9 hours)==
* Experts: D. Dutta, S. Basnet, A. Karki
+
* Experts:  
* Expected time: 1 hour
+
* Expected time: 9 hours.
* Goal: Setup coincidence timimg. Kinematic for HEEPcheck. Measure cross section.
+
* Goal:  
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-60 μA
+
  ! beam current:  || 20 μA
 
  |-
 
  |-
  ! fast raster: || 1x1mm
+
  ! fast raster: || off
 
  |-
 
  |-
  ! target: || 10cm LH2, 10cm dummy
+
  ! target: || optics targets
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! HMS/SHMS collimator: || Sieve , Centered Sieve
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! HMS/SHMS trigger: || 3/4 scin, 3/4 scin
 
  |-
 
  |-
  ! HMS angle/momentum  || 53.3 deg, +0.957 GeV/c
+
  ! HMS angle/momentum  || 30. deg, -2.0 GeV/c
 
  |-
 
  |-
  ! SHMS angle/momentum  || 25.0 deg, -1.816 GeV/c
+
  ! SHMS angle/momentum  || 30. deg, -2.0 GeV/c
 
  |}
 
  |}
*Run Plan:
+
*
== SHMS Angle and Position Matrix Optimization ==
+
== Check of ELREAL/ELCLEAN Trigger ( 1.5 hour)==
* Experts:  
+
* Experts: SImona
* Expected time: 2 hour
+
* Expected time: 1.5 hr
* Goal: SHMS angle and position matrix optimization
+
* Goal:  
 +
** Use threshold determined form previous LD2 running
 +
**Sanity check of electron triggers. 
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || 20 μA
 
  |-
 
  |-
  ! fast raster: || off
+
  ! fast raster: || 2x2mm
 
  |-
 
  |-
  ! target: || 0.5% carbon, optics targets
+
  ! target: || 10cm LH2
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! HMS/SHMS collimator: || Pion/Collimator
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! HMS/SHMS trigger: || Electron triggers
 
  |-
 
  |-
  ! HMS angle/momentum  || 25. deg, -1.6 GeV/c
+
  ! SHMS/HMS angle/momentum  || 25. deg, -3.0 GeV/c, -1.4
|-
 
! SHMS angle/momentum  || 25 deg, -1.6 GeV/c
 
 
  |}
 
  |}
*Run Plan:
 
  
= Beam energy of 6.4 GeV =
+
* Run Plan
== Initial conditions ==
 
* HMS/SHMS Conditions:
 
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! HMS angle/mom || SHMS angle/mom || Target || HMS/SHMS Trigger || Total DAQ Triggers
  |-
 
! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
 
  |-
 
  |-
  ! HMS angle/momentum  || 15 deg, -3.0 GeV/c
+
  ! 25./-3.0 || 25./-3.0 || 10cm LH2  || Only 3/4 scin (prescale trig1=0,trig2=-1,trig3=-1) || 300K
 
  |-
 
  |-
  ! SHMS angle/momentum  || 15 deg, -3.0 GeV/c
+
  ! 25./-3.0 || 25./-3.0 || 10cm LH2 || ELREAL (prescale trig1=-1,trig2=0,trig3=-1)  || 300K
  |}
 
 
 
== Superharp Scan ==
 
* Experts: Mark Jones
 
* Expected time: 1/2 hour
 
* Goal: Verify beam spot size
 
* Conditions:
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
 
  |-
 
  |-
  ! beam current: || 5 μA
+
  ! 25./-3.0 || 25./-3.0 || 10cm LH2  || ELCLEAN (prescale trig1=-1,trig2=-1,trig3=0)  || 300K
 +
  |-
 +
  ! 25./-1.4 || 25./-1.4 || 10cm LH2  || Only 3/4 scin (prescale trig1=0,trig2=-1,trig3=-1) || 300K
 
  |-
 
  |-
  ! fast raster: || off
+
  ! 25./-1.4 || 25./-1.4 || 10cm LH2  || ELREAL (prescale trig1=-1,trig2=0,trig3=-1)  || 300K
 
  |-
 
  |-
  ! target: || none
+
  ! 25./-1.4 || 25./-1.4 || 10cm LH2 || ELCLEAN (prescale trig1=-1,trig2=-1,trig3=0|| 300K
  |}
+
|}
* Ask MCC to do superharp scan with superharps IHA3H07A and IHA3H07B and put entry in ELOG. Record the 3 BPMs positions (3H07A,3H07B,3H07C) during scan.
+
== Coincidence Checkout [9 hrs] ==
** Want beam spot with  sigma_x and sigma_y below 200 um ( beam pass 1-4) and below 300 um for beam pass 5.
 
* Verify Girder BPM position to Harp positions.
 
 
 
== SHMS Tune Verification ==
 
 
* Experts:  
 
* Experts:  
 
* Expected time:  
 
* Expected time:  
Line 374: Line 337:
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || 20-50 μA
 
  |-
 
  |-
  ! fast raster: || off
+
  ! fast raster: || 2x2 mm2
 
  |-
 
  |-
  ! target: || 0.5% carbon
+
  ! target: || 10cm LH2
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! HMS/SHMS collimator: || PION/SIEVE , COLLIMATOR/CENTERED SIEVE
 
  |-
 
  |-
 
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  |-
 
  |-
  ! HMS angle/momentum  || 15. deg, -3.0 GeV/c
+
  ! HMS angle/momentum  || 27.5 deg, -3.609 GeV/c
 +
|-
 +
! SHMS angle/momentum  || 27.5 deg, +3.609 GeV/c
 +
|}
 +
* Series of runs with/without collimator on electron side and switch polarities between HMS/SHMS.
 +
* Last run is used to evaluate accidentals.
 +
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 +
|-
 +
! HMS angle || HMS momentum  || SHMS angle || HMS collimator || SHMS momentum  || SHMS collimator || Time
 +
|-
 +
! 27.5  deg ||  +3.609      || 27.5 deg || Pion  ||  -3.609 || Collimator || 30 min (4Hz at 20uA)
 +
|-
 +
! 27.5  deg ||  +3.609      || 27.5 deg || Pion  ||  -3.609 || Centered Sieve || 2 hr
 +
|-
 +
! 27.5  deg ||  -3.609      || 27.5 deg || Pion  ||  +3.609 || Collimator || 30 min (4Hz at 20uA)
 +
|-
 +
! 27.5  deg ||  -3.609      || 27.5 deg || Sieve  ||  +3.609 || Collimator || 2 hr
 
  |-
 
  |-
! SHMS angle/momentum || 15. deg, -3.0 GeV/c
+
  ! 27.5 deg || -3.609      || 35.0 deg || Pion  ||  +3.609 || Collimator || 1 hr
 
  |}
 
  |}
*
 
 
  
== Detailed Detector Checkout ==
+
== Additional Large Ytar: HMS/SHMS Angle and Position Matrix Optimization (6 hours)==
 
* Experts:  
 
* Experts:  
* Expected time: ? hour
+
* Expected time: 6 hours.
 
* Goal:  
 
* Goal:  
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || 65 μA
 +
|-
 +
! fast raster: || 2x2
 +
|-
 +
! target: || optics targets
 +
|-
 +
! HMS/SHMS collimator: || Sieve , Centered Sieve
 
  |-
 
  |-
  ! fast raster: || off
+
  ! HMS/SHMS trigger: || 3/4 scin, 3/4 scin
 
  |-
 
  |-
  ! target: || 0.5% carbon
+
  ! HMS angle/momentum  || 25.5,22 deg, -2.6,-3.2 GeV/c
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! SHMS angle/momentum  || 30.,22 deg, -2.0,-3.2 GeV/c
 +
|}
 +
*Run Plan:  Time is assuming 65uA. Take one hour long runs. Should take about 5 hours for +/-10cm data and 1 hour for +/-5cm data.
 +
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4,SCIN 3/4
+
  ! Target  || HMS angle || HMS momentum || SHMS angle || SHMS momentum  || SHMS collimator || Counts
 
  |-
 
  |-
  ! HMS angle/momentum || 15 deg, -3.0 GeV/c
+
  ! 0,+/- 10cm || 25. deg || -2.6|| 30. deg ||  -2.0 || Centered Sieve || Total of 4.0M SHMS triggers.
 
  |-
 
  |-
  ! SHMS angle/momentum || 15 deg, -3.0 GeV/c
+
  ! +/- 5cm || 22. deg || -3.2|| 22. deg ||  -3.2 || Centered Sieve || Total of 1.0M SHMS Triggers.
 
  |}
 
  |}
=== Wire Chamber ===
+
== Additional Coincidence Checkout [3 hr] ==
* SHMS Run plan:
+
* HMS Run plan:
 
 
 
=== Shower Counter Calibration Run ===
 
* SHMS Run plan:
 
* HMS Run plan:
 
 
 
=== Scintillator  ===
 
* SHMS Run plan:
 
* HMS Run plan:
 
 
 
=== Cerenkov ===
 
* SHMS Heavy Gas Cherenkov: [https://hallcweb.jlab.org/doc-private/ShowDocument?docid=819 calibration plan]
 
* HMS Run plan:
 
 
 
===Aerogel===
 
* SHMS Run plan:
 
 
 
== Set Discriminator Thresholds for PID Trigger ==
 
* Experts:
 
* Expected time:
 
* Goal:
 
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || 65 μA
 
  |-
 
  |-
  ! fast raster: || off
+
  ! fast raster: || 2x2 mm2
 
  |-
 
  |-
  ! target: || 0.5% carbon
+
  ! target: || 10cm LH2
 
  |-
 
  |-
 
  ! HMS/SHMS collimator: || PION , COLLIMATOR
 
  ! HMS/SHMS collimator: || PION , COLLIMATOR
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! HMS/SHMS trigger: || Coincidence
 
  |-
 
  |-
  ! HMS angle/momentum  || 15. deg, -3.0 GeV/c
+
  ! HMS angle/momentum  || Various
 
  |-
 
  |-
  ! SHMS angle/momentum  || 15. deg, -3.0 GeV/c
+
  ! SHMS angle/momentum  || Various
 
  |}
 
  |}
*
+
*Run Plan:
 
+
**HMS is detecting electrons and SHMS is detecting protons.
 
+
** Use HMS pion collimator and SHMS collimator.
== Defocused Tune for SHMS ==
+
** Cycle SHMS for each change when raising momentum
* Experts: Hamlet
 
* Expected time: 1 hr
 
* Goal: Have a wider y_fp to calibrate the calorimeter over regions that are not usually hit with the standard hourglass tune.
 
* Conditions:
 
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current: || 5-20 μA
+
  ! Target || Prescales || HMS angle || HMS momentum || SHMS angle  || SHMS momentum  || Time
 
  |-
 
  |-
  ! fast raster: || 2x2mm
+
  ! LH2  || ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 || 22.0  deg ||  -4.284      ||  33.3 deg  ||  +2.925 || 30 min (65Hz)
 
  |-
 
  |-
  ! target: || 10cm LH2
+
  ! 0.5% carbon || ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1  || 22.0  deg ||  -4.284      ||  33.3 deg  ||  +2.925 || 10min
 
  |-
 
  |-
  ! SHMS collimator: || Collimator
+
  ! 0.5% carbon || ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1||35.0  deg ||  -2.869      ||  22.0 deg  ||  +4.38 || 10 min
 +
|-
 +
! LH2  || ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 ||35.0  deg ||  -2.869      ||  22.0 deg  ||  +4.38 || 30 min (6Hz)
 
  |-
 
  |-
  ! SHMS trigger: || SCIN 3/4
+
  ! LH2  || ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 ||50.0  deg ||  -1.864      ||  15.3 deg  ||  +5.41 || 1.5 hrs (0.6Hz)
 
 
 
  |-
 
  |-
  ! SHMS angle/momentum || 25. deg, -3.0 GeV/c, Q2 at 1.2 times normal
+
  ! 0.5% carbon || ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1||50.deg ||  -1.864      ||  15.3 deg  ||  +5.41 || 10 min
 
  |}
 
  |}
*Run Plan:[https://github.com/MarkKJones/fall2017-plans/tree/master/defocused-tune Documents]
+
* Run until 8am when Jay Benesch in MCC will do the beam energy measurement.
  
== BCM Calibration ==
+
== Beam Energy Measurement (3 hours)==
* Experts: Dave Mack
+
* Experts: MCC, Jay Benesch
* Expected time: 2 hours
+
* Expected time: 3 hours
* Goal: BCM Calibration data including low currents to look at non-linearities
+
* Goal: Measure beam energy for elastics
* Conditions: Slit closed for zero current
+
* Conditions:  
* Procedure:  Ask MCC to ramp up and then down covering the currents below with alternating on/off and 2 minutes at each current
 
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam currents (uA):  || 0, 1, 0, 3, 0, 5, 0, 7, 0, 10, 0, 12, 0, 15, 0, 17, 0, 20
+
  ! beam current:  || 5uA
 
  |-
 
  |-
 
  ! fast raster: || off
 
  ! fast raster: || off
 
  |-
 
  |-
  ! target: || 0.5% Carbon
+
  ! target: || none
 
  |}
 
  |}
*Run Plan:
+
*MCC procedure
 
+
== Target LH2/LD2 boiling study==
== Target boiling study ==
+
* Experts: Eric Pooser
* Experts:  
+
* Expected time:
* Expected time: hour
+
* Goal: Measure target boiling.
* Goal: Measure target boiling
+
* Conditions:
* Conditions:  
 
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
|-Reminder of PHY201-02 Final Exam tomorrow (Wednesday, December 13) at 8am in regular class room - bring final exam equation sheet posted on BB.
 
! beam current:  || Take currents given below
 
 
  |-
 
  |-
  ! fast raster: || 1x1mm
+
! beam current (uA):  || 2, 7, 10, 20, 30, 40, 50, 60, 65
 +
|-
 +
  ! fast raster: || 2x2mm
 
  |-
 
  |-
  ! target: || 10cm LH2, 10cm LD2, carbon
+
  ! target: || 10cm LH2, 10cm LD2, 0.5% Carbon, *Al 10 cm Dummy only at 20 and 40 muA*
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! SHMS/HMS collimator: || Collimator/PION
 +
|-
 +
! SHMS trigger: || SCIN 3/4
 +
|-
 +
! SHMS angle/momentum:  || 15 deg / -3 GeV/c
 +
|-
 +
! HMS trigger: || SCIN 3/4
 +
|-
 +
! HMS angle/momentum: || 15 deg / -3 GeV/c
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  |}
 +
* Run Plan:
 +
** Set spectrometers to above settings
 +
** For each target, do nine separate runs for each current and take 200,000 events.
 +
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! HMS angle/momentum || 15. deg, -3 GeV/c
+
  ! Target || Trigger || Currents
 +
|-
 +
!10cm LH2 || ps1=#, rest to -1, Set # so deadtime is 20% || 2, 7, 10, 20, 30, 40, 50, 60, 65
 +
|-
 +
!10cm LD2 || ps1=#, rest to -1, Set # so  deadtime is 20% || 2, 7, 10, 20, 30, 40, 50, 60, 65
 +
|-
 +
!0.5% carbon || ps1=#, rest to -1, Set # so  deadtime is 20%  || 2, 7, 10, 20, 30, 40, 50, 60, 65
 
  |-
 
  |-
  ! SHMS angle/momentum || 15. deg, -13 GeV/c
+
  !10 cm dummy || ps1=#, rest to -1, Set # so  deadtime is 20% || 20,40
 
  |}
 
  |}
*Run Plan:
 
  
== Beam Energy Measurement ==
+
== Final  Checkout of SHMS ELREAL/ELCLEAN Trigger ( 3 hour)==
* Experts: MCC,Mark Jones, Dave Mack
+
* Experts: Simona Malace
* Expected time: ? hours
+
* Expected time: 3 hr
* Goal: Measure beam energy for carbon elastics.
+
* Goal:  
 +
** Take data to determine thresholds.
 +
**Sanity check of electron triggers.
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5uA
+
  ! beam current:  || 65 μA
 +
|-
 +
! fast raster: || 2x2mm
 +
|-
 +
! target: || 10cm LH2
 +
|-
 +
! SHMS collimator: || Collimator
 
  |-
 
  |-
  ! fast raster: || off
+
  ! SHMS trigger: || Various triggers
 
  |-
 
  |-
  ! target: || none
+
  ! SHMS angle/momentum  || 25. deg, -3.0 GeV/c, -1.4
 
  |}
 
  |}
*MCC procedure
 
  
 +
* Run Plan
 +
 +
** Take run with 3/4 and threshold at 10mV
 +
** Take run with 3/4 and thresholds at: SHMS (PRLO = 10 mV, PRHI = 15 mV, CER = 10 mV)
 +
** Take run with ELREAL only trigger
 +
** Take run with ELCLEAN trigger
 +
** Analyze results and confirm that expected efficiencies are achieved.
 +
** Lower spectrometer momentum to -1.4 GeV to increase pi/e ratio.
 +
** Repeat all of above
  
== 1H or 12C(eep)  [3 hr] ==
 
* Experts:
 
* Expected time:
 
* Goal:
 
* Conditions:
 
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current: || 20-50 μA
+
  ! SHMS angle/mom || Target || SHMS Trigger || Trigger Thresholds || Total DAQ Triggers
 +
|-
 +
!  25./-3.0 || 10cm LH2  || Only 3/4 trigger || All PID legs to 10mV || 300K
 +
|-
 +
!  25./-3.0 || 10cm LH2  || Only 3/4 trigger || SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV || 300K
 
  |-
 
  |-
  ! fast raster: || 1x1mm2
+
  ! 25./-3.0 || 10cm LH2  || Only ELREAL  || SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV  || 300K
 
  |-
 
  |-
  ! target: || 3% carbon, 10cm LH2
+
  ! 25./-3.0 || 10cm LH2 || Only ELCLEAN || SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV  || 300K
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! 25./-1.4 || 10cm LH2  || Only 3/4 trigger || All PID legs to 10mV || 300K
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! 25./-1.4 || 10cm LH2  || Only 3/4 trigger || SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV || 300K
 
  |-
 
  |-
  ! HMS angle/momentum || 27.5 deg, -3.609 GeV/c
+
  ! 25./-1.4 || 10cm LH2  || Only ELREAL || SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV || 300K
 
  |-
 
  |-
  ! SHMS angle/momentum || 27.5 deg, +3.609 GeV/c
+
  ! 25./-1.4 || 10cm LH2 || Only ELCLEAN || SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV || 300K
  |}
+
  |-
*
+
|}
  
 
+
== SHMS Elastic Single arm Checkout Additional angles (4 hours) ==
== 1H or 12C(e, e’ π) [2 hr] ==
 
 
* Experts:  
 
* Experts:  
 
* Expected time:  
 
* Expected time:  
Line 563: Line 554:
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 20-50 μA
+
  ! beam current:  || 65uA
|-
 
! fast raster: || 1x1mm2
 
 
  |-
 
  |-
  ! target: || 3% carbon, 10cm LH2
+
  ! fast raster: || 2x2mm2
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! target: || 0.5% carbon, 10cm LH2
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! SHMS collimator: || PION , COLLIMATOR
 
  |-
 
  |-
  ! HMS angle/momentum  || 16.8 deg, -3.8 GeV/c
+
  ! SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  |-
 
  |-
  ! SHMS angle/momentum  || 20.0 deg, +2.7 GeV/c
+
  ! SHMS angle/momentum  || 16,20 ,30,35 deg / 5.074,4.522,3.349,2.869 GeV
 
  |}
 
  |}
*
+
*Run plan
 +
** Take 15 min run with 0.5% carbon. Run LH2  for 10,000 events in elastic W for SHMS at 16 deg.
 +
** Take 15 min run with 0.5% carbon. Run for 10,000 events in elastic W for SHMS at 20 deg
 +
** Take 15 min run with 0.5% carbon. Run for 10,000 events in elastic W for SHMS at 30 deg
 +
** Take 15 min run with 0.5% carbon. Run for 10,000 events in elastic W for SHMS at 35 deg
  
== 1H(e’K) and 1H(e, e’K) [3 hr] ==
+
== CT Physics [53 hrs] ==
* Experts:
+
* Expected time:
 
* Goal:
 
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 20-50 μA
+
  ! beam current:  || 65 μA
 
  |-
 
  |-
  ! fast raster: || 1x1mm2
+
  ! fast raster: || 2x2 mm2
 
  |-
 
  |-
 
  ! target: || 10cm LH2
 
  ! target: || 10cm LH2
Line 594: Line 585:
 
  ! HMS/SHMS collimator: || PION , COLLIMATOR
 
  ! HMS/SHMS collimator: || PION , COLLIMATOR
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! HMS/SHMS trigger: || Coincidence
 
  |-
 
  |-
  ! HMS angle/momentum  || 25.0 deg, -2.6 GeV/c
+
  ! HMS angle/momentum  || Various
 
  |-
 
  |-
  ! SHMS angle/momentum  || 15.0 deg, +3.6 GeV/c
+
  ! SHMS angle/momentum  || Various
 
  |}
 
  |}
*
+
*Run Plan:
 
+
**HMS is detecting electrons and SHMS is detecting protons.
== Coincidence Checkout [16 hrs] ==
+
** Use HMS pion collimator and SHMS collimator.
* Experts:
+
** Keep track of good coincidence physics events (with tight PID cuts and coincidence time cut) such that we have 10000 events each for LH2 and Carbon
* Expected time:
 
* Goal:
 
* Conditions:
 
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 20-50 μA
+
  ! Target || Prescales || HMS angle || HMS momentum || SHMS angle || SHMS momentum  || Time
|-
 
  ! fast raster: || 1x1mm2
 
  |-
 
! target: || 10cm LH2
 
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION/SIEVE , COLLIMATOR/CENTERED SIEVE
+
  ! LH2  || ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 || 45.1  deg ||  -2.131      ||  17.1 deg  ||  +5.122 || 12 hrs
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! LH2  || ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 || 45.1  deg ||  -2.131      ||  17.1 deg  ||  +5.122 || 30 min
 
  |-
 
  |-
  ! HMS angle/momentum || 27.5 deg, -3.609 GeV/c
+
  ! Al. Dummy || ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 || 45.deg ||  -2.131      ||  17.1 deg  ||  +5.122 || 4 hrs
 
  |-
 
  |-
  ! SHMS angle/momentum || 27.5 deg, +3.609 GeV/c
+
  ! 6% C || ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 || 45.1  deg ||  -2.131      ||  17.1 deg  ||  +5.122 || 36 hrs
 +
|-
 +
! 6% C || ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1  || 45.1  deg ||  -2.131      ||  17.1 deg  ||  +5.122 || 30 min
 
  |}
 
  |}
*We will take a set of 1H(e,e’p) measurements to check the angle and dp/p offsets for the spectrometers. Use a current of 50 μA if possible. Rotate both HMS and SHMS to -27.5° again (or keep them there if already at that angle). Keep both HMS and SHMS at a central momentum of -3.609 GeV/c. First use the sieve slit on the SHMS side and the central Carbon optics target. Use the Particle Id. trigger, and measure about 2K singles in SHMS (that should take about one hour). Now install the 10 cm hydrogen target and measure about 2K singles in SHMS (that is again about one hour). Now take a coincidence spectrum in the same situation, again a measurement of about one hour. Remove the sieve slit on the SHMS side and use the large collimator. Measure a coincidence spectrum for one hour (rate should be 4 Hz, so this will get >10K statistics). Now install the sieve slit on the HMS side and measure another coincidence spectrum for a few hours (a few K statistics).
+
* If possible after completing the LH2 and Dummy we can move to F2 Physics program and come back to the Carbon after the F2 physics program
  
== Elastic p(ep) Checkout  ==
+
== F2 Physics ==
 +
*[https://hallcweb.jlab.org/wiki/index.php/Main_Page#F2_Experiment_.28E12-10-002.29_L.2FT_measurement_Run_Plan Run plan]
 +
 
 +
== Remaining Commissioning ==
 +
=== SHMS Elastic Single arm Checkout Additional angles (4 hours) ===
 
* Experts:  
 
* Experts:  
 
* Expected time:  
 
* Expected time:  
Line 632: Line 622:
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 20-50 μA
+
  ! beam current:  || 65uA
 
  |-
 
  |-
  ! fast raster: || 1x1mm2
+
  ! fast raster: || 2x2mm2
 
  |-
 
  |-
 
  ! target: || 10cm LH2
 
  ! target: || 10cm LH2
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! SHMS collimator: || COLLIMATOR/Center sieve
|-
 
! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
 
  |-
 
  |-
  ! HMS angle/momentum  || 27.5 deg, -3.609 GeV/c
+
  ! SHMS trigger: || SCIN 3/4
 
  |-
 
  |-
  ! SHMS angle/momentum  || 27.5 deg, +3.609 GeV/c
+
  ! SHMS angle/momentum  || 25 ,30  / -3.911,-3.349
 
  |}
 
  |}
*Take runs to acquire roughly 10K events for HMS (use the large pion collimator!) at angles of 27.5°, 28.8°, 30.1°, 24.9°, and 26.. For SHMS at identical angles but also at angles of 31.8°, 33.5°, 35.2° and 23.. Roughly, at the central setting you need 45 minutes to acquire 10K statistics, and less at the lower angles, but perhaps 1.5 hour at 30.1°, and up to 5 hours at the largest SHMS angle of 35..
+
*Run plan
 +
**Take data at SHMS angle = 25 and momentum = -3.911 with collimator for 30 minutes.
 +
**Take data at SHMS angle = 25 and momentum = -3.911 with centered Sieve for 1 hour.
 +
**Take data at SHMS angle = 25 and momentum = -3.6 with collimator for 30 minutes.
 +
**Take data at SHMS angle = 25 and momentum = -3.349 with collimator for 30 minutes.
 +
**Take data at SHMS angle = 30 and momentum = -3.349 with collimator for 1 hour.
 +
**Take data at SHMS angle = 30 and momentum = -3.349 with centered sieve for 2 hour.
 +
 
 +
 +
 
  
== HMS/SHMS Angle and Position Matrix Optimization ==
+
 
 +
===22 deg Ytar: SHMS Angle and Position Matrix Optimization (1 hours)===
 
* Experts:  
 
* Experts:  
* Expected time:  
+
* Expected time: 1 hours.
* Goal:  
+
* Goal: Need more optics data for SHMS at large angles.
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 20-50 μA
+
  ! beam current:  || 65 μA
 
  |-
 
  |-
  ! fast raster: || off
+
  ! fast raster: || 2x2
 
  |-
 
  |-
  ! target: || optics targets
+
  ! target: || 0,+/- 10cm
 
  |-
 
  |-
  ! HMS/SHMS collimator: || Sieve , Centered Sieve
+
  ! SHMS collimator: || Centered Sieve,Shifted Sieve
 
  |-
 
  |-
  ! HMS/SHMS trigger: || ,  
+
  ! SHMS trigger: || ELREAL
 +
  |-
 +
! SHMS angle/momentum  || 22 deg, -3.2 GeV/c
 +
|}
 +
*Run Plan: Take during switch in HMS polarity.  Time is assuming 65uA. 
 +
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 +
! Target  || SHMS angle || SHMS momentum  || SHMS collimator || Time
 
  |-
 
  |-
  ! HMS angle/momentum  || 25. deg, -3.0 GeV/c
+
  ! 0,+/- 10cm || 22. deg ||  -3.2 || Centered Sieve || 30 minutes
 
  |-
 
  |-
  ! SHMS angle/momentum  || 25. deg, -3.0 GeV/c
+
  ! 0,+/- 10cm || 22. deg ||  -3.2 || Shifted Sieve || 30 minutes
 
  |}
 
  |}
*
 
  
== HMS Angle and position matrix optimization for large ytgt  ==
+
=== SHMS Low momentum electrons and large angle (3 hours)===
* Experts:  
+
* Experts: Eric Christy
* Expected time:  
+
* Expected time: 3 hours.
* Goal:  Calibrate HMS ytgt, yptar and xptar for 10cm target.
+
* Goal:   
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 20-50 μA
+
  ! beam current:  || 65 μA, 40uA (Aluminum dummy)
 +
|-
 +
! fast raster: || 2x2
 
  |-
 
  |-
  ! fast raster: || off
+
  ! target: || 10cm Lh2, 10cm Al dummy
 
  |-
 
  |-
  ! target: || optics targets
+
  ! SHMS collimator: || collimator
 
  |-
 
  |-
  ! HMS  || Sieve , Centered Sieve
+
  ! SHMS trigger: || ELREAL
 +
  |-
 +
! SHMS angle/momentum  || 35 deg, -2.6 GeV/c
 +
|}
 +
*Run Plan: Take while HMS with positive polarity is taken. Time is assuming 65uA. 
 +
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 +
! Target  || SHMS angle || SHMS momentum  || Time
 
  |-
 
  |-
  ! HMS trigger: || ,
+
  !10cm Lh2 || 35. deg ||  -2.6  || 2 hours
 
  |-
 
  |-
  ! HMS angle/momentum  || 50. deg, -2.0 GeV/c
+
  ! 10cm || 35. deg ||  -2.6  || 20 minutes
 
 
 
  |}
 
  |}
*Run Plan:
 
  
== Use GEM to check out SHMS optics ==
+
===30 deg  Ytar: HMS/SHMS Angle and Position Matrix Optimization (3 hours)===
 
* Experts:  
 
* Experts:  
* Expected time:  
+
* Expected time: 3 hours.
* Goal:
+
* Goal: Need more optics data for SHMS at large angles.
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || <1 μA
+
  ! beam current:  || 65 μA
 
  |-
 
  |-
  ! fast raster: || off
+
  ! fast raster: || 2x2
 
  |-
 
  |-
 
  ! target: || optics targets
 
  ! target: || optics targets
 
  |-
 
  |-
  ! SHMS collimator: || Collimator
+
  ! SHMS collimator: || Centered Sieve
 +
|-
 +
! SHMS trigger: || ELREAL
 
  |-
 
  |-
  ! SHMS trigger: || 3/4 Scin + Cer
+
  ! SHMS angle/momentum  || 30. deg, -2.0 GeV/c
 +
|}
 +
*Run Plan:  Time is assuming 65uA. Take one hour long runs.
 +
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 +
! Target  ||  SHMS angle || SHMS momentum  || SHMS collimator || Time
 
  |-
 
  |-
  ! SHMS angle/momentum  || 25. deg, -2.0 GeV/c
+
  ! 0,+/- 10cm || 30. deg ||  -2.0 || Centered Sieve || 3 hours
 
  |}
 
  |}
*Run Plan:
 
  
== Check spectrometer pointing  ==
+
=== Repeat Target LH2 boiling study with new SHMS sheilding===
 
* Experts:  
 
* Experts:  
* Expected time:  
+
* Expected time:
* Goal: Measure the HMS/SHMS spectrometer pointing
+
* Goal: With new SHMS shielding reconfiguration, repeat LH2 measurement and see if background reduced.
* Conditions:  
+
* Conditions:
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 20-50 μA
+
  ! beam current (uA):  || 10, 30 , 65
 
  |-
 
  |-
  ! fast raster: || off
+
  ! fast raster: || 2x2mm
 
  |-
 
  |-
  ! target: || 3% carbon
+
  ! target: || 10cm LH2
 
  |-
 
  |-
  ! HMS/SHMS collimator: || Sieve, Centered sieve
+
  ! SHMS/HMS collimator: || Collimator/PION
 +
|-
 +
! SHMS trigger: || SCIN 3/4
 
  |-
 
  |-
  ! HMS/SHMS trigger: || ,
+
  ! SHMS angle/momentum: || 15 deg / -3 GeV/c
 +
 +
|}
 +
* Run Plan:
 +
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! HMS angle/momentum  || 12.-60 deg, -3.0 GeV/c
+
  ! Target || Trigger || Currents
|-
+
|-
! SHMS angle/momentum  || 7.5-40 deg, -3.0 GeV/c
+
!10cm LH2 || ps1=#, rest to -1, Set # so deadtime is 20% || 10, 30, 65
 
  |}
 
  |}
*
 
  
= Beam energy of 8.8 GeV =
+
== Lower priority ==
 +
= Beam energy of 10.6 GeV =
  
 
== Beam Energy Measurement ==
 
== Beam Energy Measurement ==
Line 753: Line 773:
 
  |}
 
  |}
 
*MCC procedure
 
*MCC procedure
== SHMS Tune Verification ==
+
 
 +
 
 +
== HMS/SHMS Tune Verification ==
 
* Experts:  
 
* Experts:  
 
* Expected time:  
 
* Expected time:  
 
* Goal:  
 
* Goal:  
 +
**Mix of ep elastic data,  and carbon data to check SHMS tune.
 +
**Also LH2 inelastic to calibrate the calorimeter.
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || max current μA
 
  |-
 
  |-
  ! fast raster: || off
+
  ! fast raster: || 2x2
 
  |-
 
  |-
  ! target: || 3% carbon
+
  ! target: || 1.5% carbon, 10 LH2
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! HMS/SHMS collimator: || PION/SIEVE , COLLIMATOR/Centered Sieve
 
  |-
 
  |-
 
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
 
  |-
 
  |-
  ! HMS angle/momentum  ||  
+
  ! HMS angle/momentum  || see table
 
  |-
 
  |-
  ! SHMS angle/momentum  ||  
+
  ! SHMS angle/momentum  || see table
 
  |}
 
  |}
*
+
*Run Plan
 
 
== 1H(eep) ==
 
 
 
 
 
= Beam energy of 10.6 GeV =
 
 
 
== Beam Energy Measurement ==
 
* Experts: MCC,Mark Jones, Dave Mack
 
* Expected time: ? hours
 
* Goal: Measure beam energy for carbon elastics.
 
* Conditions:
 
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current: || 5uA
+
  ! Target || HMS angle || HMS momentum|| HMS collimator  || SHMS angle  || SHMS momentum  || SHMS collimator  || Time
 +
|-
 +
! LH2  || 18.5  deg ||  -6.693      || pion ||  8.5 deg  ||  -9.430 || Collimator || 30 min
 +
|-
 +
! LH2 ||  18.5 deg ||  -6.693  || Pion  ||  8.5 deg  ||  -7.3 || Collimator || 30 min
 +
|-
 +
! 1.5% carbon ||  18.5 deg ||  -5.816  || Sieve  ||  8.5 deg  ||  -7.3 || Centered Sieve || 1 hr
 +
|-
 +
! LH2  || 18.5  deg ||  -5.816    || Pion ||  16.5 deg  || -7.234  || Collimator || 1 hr
 
  |-
 
  |-
  ! fast raster: || off
+
  ! LH2  || 18.5  deg ||  -5.816    || Pion ||  16.5 deg  || -5.5  || Collimator || 1 hr
 
  |-
 
  |-
  ! target: || none
+
  ! 1.5% carbon || 18.5  deg ||  -5.816    || Sieve  ||  16.5 deg  ||  -5.5 || Centered Sieve || 2 hr
 
  |}
 
  |}
*MCC procedure
 
  
== 1H(eep) ==
+
== BCM Calibration ( 1 hour) ==
 +
*
  
== SHMS Tune Verification ==
+
== Use GEM to check out SHMS optics ==
* Experts:  
+
* Experts: Latif
 
* Expected time:  
 
* Expected time:  
* Goal:  
+
* Goal:
 
* Conditions:  
 
* Conditions:  
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
{|class="wikitable" style="margin-left: 60px; margin-right: auto; border: none;"
 
  |-
 
  |-
  ! beam current:  || 5-20 μA
+
  ! beam current:  || <1 μA
 
  |-
 
  |-
 
  ! fast raster: || off
 
  ! fast raster: || off
 
  |-
 
  |-
  ! target: || 3% carbon
+
  ! target: || optics targets
 
  |-
 
  |-
  ! HMS/SHMS collimator: || PION , COLLIMATOR
+
  ! SHMS collimator: || Collimator
 
  |-
 
  |-
  ! HMS/SHMS trigger: || SCIN 3/4, SCIN 3/4
+
  ! SHMS trigger: || 3/4 Scin + Cer
 
  |-
 
  |-
  ! HMS angle/momentum  ||  
+
  ! SHMS angle/momentum  || 25. deg, -2.0 GeV/c
|-
 
! SHMS angle/momentum  ||
 
 
  |}
 
  |}
*
+
*Run Plan:

Latest revision as of 14:53, 29 January 2018

Beam energy of 2.2 GeV

Beam energy of 6.4 GeV

Initial conditions

  • HMS/SHMS Conditions:
HMS/SHMS collimator: PION , COLLIMATOR
HMS/SHMS trigger: SCIN 3/4, SCIN 3/4
HMS angle/momentum 15 deg, -3.0 GeV/c
SHMS angle/momentum 15 deg, -3.0 GeV/c

Beam Checkout with Superharps and Beam Position Monitors (3 hours)

  • Experts: Mark Jones, Deb Biswas, Thir Guatam
  • Expected time: 3 hours
  • Goals: Initial measurement of beam spot size. Followed by calibration of girder BPMs at 5,30 and 60uA. Measure raster size with superharps.
  • Conditions:
beam current: 5,30 and 60 μA
fast raster: off
target: none
  • Runplan: pdf file
  • Ask MCC to do superharp scan with superharps IHA3H07A and IHA3H07B and put entry in ELOG. Record the 3 BPMs positions (3H07A,3H07B,3H07C) during scan.
    • Want beam spot with sigma_x and sigma_y below 200 um ( beam pass 1-4) and below 300 um for beam pass 5.
  • Verify Girder BPM position to Harp positions.

Center beam on C-hole target ( 1 hour)

  • Experts:
  • Expected time: 1 hour
  • Goal: Center beam on carbon hole target
  • Conditions:
beam current: 5 μA
fast raster: 3x3mm
target: carbon hole
HMS/SHMS collimator: PION , COLLIMATOR
HMS/SHMS trigger: SCIN 3/4, SCIN 3/4
HMS angle/momentum 15 deg, -3.0 GeV/c
SHMS angle/momentum 15 deg, -3.0 GeV/c
  • Run plan: Procedure
  • Once hole is found, take 20 minutes run at 20uA for good statistics

Detailed Detector Checkout ( 2 hour)

  • Experts:
  • Expected time: 2 hour
  • Prerequisite: Eric Pooser will do invasive checkout of HMS/SHMS trigger with beam.
  • Conditions:
beam current: 20 μA
fast raster: off
target: 0.5% carbon
HMS/SHMS collimator: PION , COLLIMATOR
HMS/SHMS trigger: SCIN 3/4,SCIN 3/4
HMS angle/momentum 15 deg, -3.0 GeV/c
SHMS angle/momentum 15 deg, -3.0 GeV/c

Trigger

  • Set HMS/SHMS trigger threshold for PID trigger section to 10 mV.
  • Software cuts can be placed on trigger ADC data to study efficiencies.

Cerenkov

  • SHMS Noble Gas Run Plan: Scan of HV ( Eric Pooser)
Run 1 HV Settings: PMT1 = 2200 V, PMT2 = 2230 V, PMT3 = 2115, PMT4 = 2030
Run 2 HV Settings: PMT1 = 2300 V, PMT2 = 2320 V, PMT3 = 2215, PMT4 = 2130
    • These are the spring 2017 KPP HV settings for reference: NGC1 : 2255 V, NGC2 : 2280 V, NGC3 : 2165 V, NGC4 : 2087 V
    • We will also need to check the NGCER sum the PID trigger circuit to ensure that we are not saturating the FADC channel
  • Run plan (series of 15 minutes runs)
Run HMS DAQ SHMS DAQ Comments
1 No data taking Only 3/4 scin trigger Checkout of HMS 3/4 trigger ; SHMS NGC HV NGC1 : 2255 V, NGC2 : 2280 V, NGC3 : 2165 V, NGC4 : 2087 V
2 Only 3/4 scin trigger No data taking Checkout of SHMS 3/4 trigger
3 Only 3/4 scin trigger Only 3/4 scin trigger Checkout of HMS ELCLEAN/ELREAL trigger; SHMS NGC HV PMT1 = 2200 V, PMT2 = 2230 V, PMT3 = 2115, PMT4 = 2030
4 Only 3/4 scin trigger Only 3/4 scin trigger Checkout of HMS ELCLEAN/ELREAL trigger ; SHMS NGC HV PMT1 = 2300 V, PMT2 = 2320 V, PMT3 = 2215, PMT4 = 2130
5 Only ELCLEAN trigger Only 3/4 scin trigger Checkout of SHMS ELCLEAN/ELREAL trigger
6 Only ELREAL trigger Only 3/4 scin trigger Checkout of SHMS ELCLEAN/ELREAL trigger
7 ELREAL trigger, prescale 3/4 SCIN Only ELCLEAN
8 ELCLEAN trigger, prescale 3/4 SCIN Only ELREAL
9 ELCLEAN trigger, different prescale 3/4 SCIN ELREAL, prescale 3/4 scin

Checkout of SHMS/HMS focal plane tune ( 1 hour)

  • Experts:
  • Expected time: 1 hour
  • Goal: Look at focal plane with sieve to check tune
  • Conditions:
beam current: 20 μA
fast raster: off
target: 0.5% carbon
HMS/SHMS collimator: SIEVE , Centered sieve
HMS/SHMS trigger: SCIN 3/4,SCIN 3/4
HMS angle/momentum 15 deg, -3.0 GeV/c
SHMS angle/momentum 15 deg, -3.0 GeV/c

Different Pi/e ratios ( 1.5 hour)

  • Experts: SImona
  • Expected time: 1.5 hr
  • Goal:
    • Runs with different central momentum and different pi/e ratios.
    • Two runs with LH2 and one with LD2
    • Take each setting with only 3/4 scin trigger and for 30 minutes
    • Set PID tirgger thresholds to 10 mV. Offline will determine thresholds to test later.
  • Conditions:
beam current: 5-20 μA
fast raster: 2x2mm
target: 10cm LH2, 10cm LD2
HMS/SHMS collimator: Pion/Collimator
HMS/SHMS trigger: SCIN 3/4 / SCIN 3/4
SHMS/HMS angle/momentum 25. deg, -3.0 GeV/c, -1.4
  • Run Plan
HMS angle/mom SHMS angle/mom Target HMS/SHMS Trigger
25./-3.0 25./-3.0 10cm LH2 Only 3/4 scin
25./-1.4 25./-1.4 10cm LH2 Only 3/4 scin
25./-1.4 25./-1.4 10cm LD2 Only 3/4 scin

Defocused Tune for SHMS/HMS ( 1 hour)

  • Experts: Hamlet
  • Expected time: 1 hr
  • Goal: Have a wider y_fp to calibrate the calorimeter over regions that are not usually hit with the standard hourglass tune.
  • Conditions:
beam current: 5-20 μA
fast raster: 2x2mm
target: 10cm LH2
HMS/SHMS collimator: Pion/Collimator
HMS/SHMS trigger: SCIN 3/4 / SCIN 3/4
SHMS/HMS angle/momentum 25. deg, -3.0 GeV/c, Q2 at 1.2 times normal

Elastic p(ep) Checkout Small angle (2 hours)

  • Experts:
  • Expected time:
  • Goal:
  • Conditions:
beam current: 10 μA
fast raster: 1x1mm2
target: 10cm LH2
HMS/SHMS collimator: PION , COLLIMATOR
HMS/SHMS trigger: SCIN 3/4, SCIN 3/4
HMS angle/momentum 13.5/16. deg / 5.398/5.074 GeV
SHMS angle/momentum 8.,10.,13.5 deg / 6.017,5.814,5.398 GeV
  • Run plan
HMS Angle/Mom HMS rate SHMS Angle/Mom SHMS rate Run time
13.5/5.398 300 8./6.017 3300 Hz 15 minutes
13.5/5.398 300 10./5.817 1000 30 minutes
16.0/5.074 100 13.5/5.398 150 60 minutes

HMS/SHMS Angle and Position Matrix Optimization (5 hours)

  • Experts:
  • Expected time: 5 hours.
  • Goal:
  • Conditions:
beam current: 20 μA ( more is better)
fast raster: off
target: optics targets
HMS/SHMS collimator: Sieve , Centered/Shifted Sieve
HMS/SHMS trigger: 3/4 scin, 3/4 scin
HMS angle/momentum 15 and 22. deg,
SHMS angle/momentum 15. and 22. deg,
  • Series of runs changing target.
    • SHMS has two sieves with the holes shifted in the horizontal.
    • HMS has only one sieve which will always be used.
    • No raster.
    • Time is assuming 20uA.
Target HMS angle HMS momentum SHMS angle SHMS momentum SHMS collimator Time
0,+/- 10cm 15. deg -4.0 15. deg -4.0 Centered Sieve 30 min
0,+/- 10cm 15. deg -4.0 15. deg -4.0 Shifted Sieve 30 min
+/- 5cm 15. deg -4.0 15. deg -4.0 Centered Sieve 30 min
+/- 5cm 15. deg -4.0 15. deg -4.0 Shifted Sieve 30 min
0,+/- 10cm 22. deg -3.2 22. deg -3.2 Centered Sieve 1.5 hr
0,+/- 10cm 22. deg -3.2 22. deg -3.2 Shifted Sieve 1.5 hr

Large Ytar: HMS/SHMS Angle and Position Matrix Optimization (9 hours)

  • Experts:
  • Expected time: 9 hours.
  • Goal:
  • Conditions:
beam current: 20 μA
fast raster: off
target: optics targets
HMS/SHMS collimator: Sieve , Centered Sieve
HMS/SHMS trigger: 3/4 scin, 3/4 scin
HMS angle/momentum 30. deg, -2.0 GeV/c
SHMS angle/momentum 30. deg, -2.0 GeV/c

Check of ELREAL/ELCLEAN Trigger ( 1.5 hour)

  • Experts: SImona
  • Expected time: 1.5 hr
  • Goal:
    • Use threshold determined form previous LD2 running
    • Sanity check of electron triggers.
  • Conditions:
beam current: 20 μA
fast raster: 2x2mm
target: 10cm LH2
HMS/SHMS collimator: Pion/Collimator
HMS/SHMS trigger: Electron triggers
SHMS/HMS angle/momentum 25. deg, -3.0 GeV/c, -1.4
  • Run Plan
HMS angle/mom SHMS angle/mom Target HMS/SHMS Trigger Total DAQ Triggers
25./-3.0 25./-3.0 10cm LH2 Only 3/4 scin (prescale trig1=0,trig2=-1,trig3=-1) 300K
25./-3.0 25./-3.0 10cm LH2 ELREAL (prescale trig1=-1,trig2=0,trig3=-1) 300K
25./-3.0 25./-3.0 10cm LH2 ELCLEAN (prescale trig1=-1,trig2=-1,trig3=0) 300K
25./-1.4 25./-1.4 10cm LH2 Only 3/4 scin (prescale trig1=0,trig2=-1,trig3=-1) 300K
25./-1.4 25./-1.4 10cm LH2 ELREAL (prescale trig1=-1,trig2=0,trig3=-1) 300K
25./-1.4 25./-1.4 10cm LH2 ELCLEAN (prescale trig1=-1,trig2=-1,trig3=0) 300K

Coincidence Checkout [9 hrs]

  • Experts:
  • Expected time:
  • Goal:
  • Conditions:
beam current: 20-50 μA
fast raster: 2x2 mm2
target: 10cm LH2
HMS/SHMS collimator: PION/SIEVE , COLLIMATOR/CENTERED SIEVE
HMS/SHMS trigger: SCIN 3/4, SCIN 3/4
HMS angle/momentum 27.5 deg, -3.609 GeV/c
SHMS angle/momentum 27.5 deg, +3.609 GeV/c
  • Series of runs with/without collimator on electron side and switch polarities between HMS/SHMS.
  • Last run is used to evaluate accidentals.
HMS angle HMS momentum SHMS angle HMS collimator SHMS momentum SHMS collimator Time
27.5 deg +3.609 27.5 deg Pion -3.609 Collimator 30 min (4Hz at 20uA)
27.5 deg +3.609 27.5 deg Pion -3.609 Centered Sieve 2 hr
27.5 deg -3.609 27.5 deg Pion +3.609 Collimator 30 min (4Hz at 20uA)
27.5 deg -3.609 27.5 deg Sieve +3.609 Collimator 2 hr
27.5 deg -3.609 35.0 deg Pion +3.609 Collimator 1 hr

Additional Large Ytar: HMS/SHMS Angle and Position Matrix Optimization (6 hours)

  • Experts:
  • Expected time: 6 hours.
  • Goal:
  • Conditions:
beam current: 65 μA
fast raster: 2x2
target: optics targets
HMS/SHMS collimator: Sieve , Centered Sieve
HMS/SHMS trigger: 3/4 scin, 3/4 scin
HMS angle/momentum 25.5,22 deg, -2.6,-3.2 GeV/c
SHMS angle/momentum 30.,22 deg, -2.0,-3.2 GeV/c
  • Run Plan: Time is assuming 65uA. Take one hour long runs. Should take about 5 hours for +/-10cm data and 1 hour for +/-5cm data.
Target HMS angle HMS momentum SHMS angle SHMS momentum SHMS collimator Counts
0,+/- 10cm 25. deg -2.6 30. deg -2.0 Centered Sieve Total of 4.0M SHMS triggers.
+/- 5cm 22. deg -3.2 22. deg -3.2 Centered Sieve Total of 1.0M SHMS Triggers.

Additional Coincidence Checkout [3 hr]

  • Conditions:
beam current: 65 μA
fast raster: 2x2 mm2
target: 10cm LH2
HMS/SHMS collimator: PION , COLLIMATOR
HMS/SHMS trigger: Coincidence
HMS angle/momentum Various
SHMS angle/momentum Various
  • Run Plan:
    • HMS is detecting electrons and SHMS is detecting protons.
    • Use HMS pion collimator and SHMS collimator.
    • Cycle SHMS for each change when raising momentum
Target Prescales HMS angle HMS momentum SHMS angle SHMS momentum Time
LH2 ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 22.0 deg -4.284 33.3 deg +2.925 30 min (65Hz)
0.5% carbon ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 22.0 deg -4.284 33.3 deg +2.925 10min
0.5% carbon ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 35.0 deg -2.869 22.0 deg +4.38 10 min
LH2 ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 35.0 deg -2.869 22.0 deg +4.38 30 min (6Hz)
LH2 ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 50.0 deg -1.864 15.3 deg +5.41 1.5 hrs (0.6Hz)
0.5% carbon ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 50.0 deg -1.864 15.3 deg +5.41 10 min
  • Run until 8am when Jay Benesch in MCC will do the beam energy measurement.

Beam Energy Measurement (3 hours)

  • Experts: MCC, Jay Benesch
  • Expected time: 3 hours
  • Goal: Measure beam energy for elastics
  • Conditions:
beam current: 5uA
fast raster: off
target: none
  • MCC procedure

Target LH2/LD2 boiling study

  • Experts: Eric Pooser
  • Expected time:
  • Goal: Measure target boiling.
  • Conditions:
beam current (uA): 2, 7, 10, 20, 30, 40, 50, 60, 65
fast raster: 2x2mm
target: 10cm LH2, 10cm LD2, 0.5% Carbon, *Al 10 cm Dummy only at 20 and 40 muA*
SHMS/HMS collimator: Collimator/PION
SHMS trigger: SCIN 3/4
SHMS angle/momentum: 15 deg / -3 GeV/c
HMS trigger: SCIN 3/4
HMS angle/momentum: 15 deg / -3 GeV/c
  • Run Plan:
    • Set spectrometers to above settings
    • For each target, do nine separate runs for each current and take 200,000 events.
Target Trigger Currents
10cm LH2 ps1=#, rest to -1, Set # so deadtime is 20% 2, 7, 10, 20, 30, 40, 50, 60, 65
10cm LD2 ps1=#, rest to -1, Set # so deadtime is 20% 2, 7, 10, 20, 30, 40, 50, 60, 65
0.5% carbon ps1=#, rest to -1, Set # so deadtime is 20% 2, 7, 10, 20, 30, 40, 50, 60, 65
10 cm dummy ps1=#, rest to -1, Set # so deadtime is 20% 20,40

Final Checkout of SHMS ELREAL/ELCLEAN Trigger ( 3 hour)

  • Experts: Simona Malace
  • Expected time: 3 hr
  • Goal:
    • Take data to determine thresholds.
    • Sanity check of electron triggers.
  • Conditions:
beam current: 65 μA
fast raster: 2x2mm
target: 10cm LH2
SHMS collimator: Collimator
SHMS trigger: Various triggers
SHMS angle/momentum 25. deg, -3.0 GeV/c, -1.4
  • Run Plan
    • Take run with 3/4 and threshold at 10mV
    • Take run with 3/4 and thresholds at: SHMS (PRLO = 10 mV, PRHI = 15 mV, CER = 10 mV)
    • Take run with ELREAL only trigger
    • Take run with ELCLEAN trigger
    • Analyze results and confirm that expected efficiencies are achieved.
    • Lower spectrometer momentum to -1.4 GeV to increase pi/e ratio.
    • Repeat all of above
SHMS angle/mom Target SHMS Trigger Trigger Thresholds Total DAQ Triggers
25./-3.0 10cm LH2 Only 3/4 trigger All PID legs to 10mV 300K
25./-3.0 10cm LH2 Only 3/4 trigger SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV 300K
25./-3.0 10cm LH2 Only ELREAL SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV 300K
25./-3.0 10cm LH2 Only ELCLEAN SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV 300K
25./-1.4 10cm LH2 Only 3/4 trigger All PID legs to 10mV 300K
25./-1.4 10cm LH2 Only 3/4 trigger SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV 300K
25./-1.4 10cm LH2 Only ELREAL SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV 300K
25./-1.4 10cm LH2 Only ELCLEAN SHMS PID legs to: PRLO = 10mV, PRHI = 15 mV, CER =10 mV 300K

SHMS Elastic Single arm Checkout Additional angles (4 hours)

  • Experts:
  • Expected time:
  • Goal:
  • Conditions:
beam current: 65uA
fast raster: 2x2mm2
target: 0.5% carbon, 10cm LH2
SHMS collimator: PION , COLLIMATOR
SHMS trigger: SCIN 3/4, SCIN 3/4
SHMS angle/momentum 16,20 ,30,35 deg / 5.074,4.522,3.349,2.869 GeV
  • Run plan
    • Take 15 min run with 0.5% carbon. Run LH2 for 10,000 events in elastic W for SHMS at 16 deg.
    • Take 15 min run with 0.5% carbon. Run for 10,000 events in elastic W for SHMS at 20 deg
    • Take 15 min run with 0.5% carbon. Run for 10,000 events in elastic W for SHMS at 30 deg
    • Take 15 min run with 0.5% carbon. Run for 10,000 events in elastic W for SHMS at 35 deg

CT Physics [53 hrs]

  • Conditions:
beam current: 65 μA
fast raster: 2x2 mm2
target: 10cm LH2
HMS/SHMS collimator: PION , COLLIMATOR
HMS/SHMS trigger: Coincidence
HMS angle/momentum Various
SHMS angle/momentum Various
  • Run Plan:
    • HMS is detecting electrons and SHMS is detecting protons.
    • Use HMS pion collimator and SHMS collimator.
    • Keep track of good coincidence physics events (with tight PID cuts and coincidence time cut) such that we have 10000 events each for LH2 and Carbon
Target Prescales HMS angle HMS momentum SHMS angle SHMS momentum Time
LH2 ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 45.1 deg -2.131 17.1 deg +5.122 12 hrs
LH2 ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 45.1 deg -2.131 17.1 deg +5.122 30 min
Al. Dummy ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 45.1 deg -2.131 17.1 deg +5.122 4 hrs
6% C ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 45.1 deg -2.131 17.1 deg +5.122 36 hrs
6% C ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 45.1 deg -2.131 17.1 deg +5.122 30 min
  • If possible after completing the LH2 and Dummy we can move to F2 Physics program and come back to the Carbon after the F2 physics program

F2 Physics

Remaining Commissioning

SHMS Elastic Single arm Checkout Additional angles (4 hours)

  • Experts:
  • Expected time:
  • Goal:
  • Conditions:
beam current: 65uA
fast raster: 2x2mm2
target: 10cm LH2
SHMS collimator: COLLIMATOR/Center sieve
SHMS trigger: SCIN 3/4
SHMS angle/momentum 25 ,30 / -3.911,-3.349
  • Run plan
    • Take data at SHMS angle = 25 and momentum = -3.911 with collimator for 30 minutes.
    • Take data at SHMS angle = 25 and momentum = -3.911 with centered Sieve for 1 hour.
    • Take data at SHMS angle = 25 and momentum = -3.6 with collimator for 30 minutes.
    • Take data at SHMS angle = 25 and momentum = -3.349 with collimator for 30 minutes.
    • Take data at SHMS angle = 30 and momentum = -3.349 with collimator for 1 hour.
    • Take data at SHMS angle = 30 and momentum = -3.349 with centered sieve for 2 hour.



22 deg Ytar: SHMS Angle and Position Matrix Optimization (1 hours)

  • Experts:
  • Expected time: 1 hours.
  • Goal: Need more optics data for SHMS at large angles.
  • Conditions:
beam current: 65 μA
fast raster: 2x2
target: 0,+/- 10cm
SHMS collimator: Centered Sieve,Shifted Sieve
SHMS trigger: ELREAL
SHMS angle/momentum 22 deg, -3.2 GeV/c
  • Run Plan: Take during switch in HMS polarity. Time is assuming 65uA.
Target SHMS angle SHMS momentum SHMS collimator Time
0,+/- 10cm 22. deg -3.2 Centered Sieve 30 minutes
0,+/- 10cm 22. deg -3.2 Shifted Sieve 30 minutes

SHMS Low momentum electrons and large angle (3 hours)

  • Experts: Eric Christy
  • Expected time: 3 hours.
  • Goal:
  • Conditions:
beam current: 65 μA, 40uA (Aluminum dummy)
fast raster: 2x2
target: 10cm Lh2, 10cm Al dummy
SHMS collimator: collimator
SHMS trigger: ELREAL
SHMS angle/momentum 35 deg, -2.6 GeV/c
  • Run Plan: Take while HMS with positive polarity is taken. Time is assuming 65uA.
Target SHMS angle SHMS momentum Time
10cm Lh2 35. deg -2.6 2 hours
10cm 35. deg -2.6 20 minutes

30 deg Ytar: HMS/SHMS Angle and Position Matrix Optimization (3 hours)

  • Experts:
  • Expected time: 3 hours.
  • Goal: Need more optics data for SHMS at large angles.
  • Conditions:
beam current: 65 μA
fast raster: 2x2
target: optics targets
SHMS collimator: Centered Sieve
SHMS trigger: ELREAL
SHMS angle/momentum 30. deg, -2.0 GeV/c
  • Run Plan: Time is assuming 65uA. Take one hour long runs.
Target SHMS angle SHMS momentum SHMS collimator Time
0,+/- 10cm 30. deg -2.0 Centered Sieve 3 hours

Repeat Target LH2 boiling study with new SHMS sheilding

  • Experts:
  • Expected time:
  • Goal: With new SHMS shielding reconfiguration, repeat LH2 measurement and see if background reduced.
  • Conditions:
beam current (uA): 10, 30 , 65
fast raster: 2x2mm
target: 10cm LH2
SHMS/HMS collimator: Collimator/PION
SHMS trigger: SCIN 3/4
SHMS angle/momentum: 15 deg / -3 GeV/c
  • Run Plan:
Target Trigger Currents
10cm LH2 ps1=#, rest to -1, Set # so deadtime is 20% 10, 30, 65

Lower priority

Beam energy of 10.6 GeV

Beam Energy Measurement

  • Experts: MCC,Mark Jones, Dave Mack
  • Expected time: ? hours
  • Goal: Measure beam energy for carbon elastics.
  • Conditions:
beam current: 5uA
fast raster: off
target: none
  • MCC procedure


HMS/SHMS Tune Verification

  • Experts:
  • Expected time:
  • Goal:
    • Mix of ep elastic data, and carbon data to check SHMS tune.
    • Also LH2 inelastic to calibrate the calorimeter.
  • Conditions:
beam current: max current μA
fast raster: 2x2
target: 1.5% carbon, 10 LH2
HMS/SHMS collimator: PION/SIEVE , COLLIMATOR/Centered Sieve
HMS/SHMS trigger: SCIN 3/4, SCIN 3/4
HMS angle/momentum see table
SHMS angle/momentum see table
  • Run Plan
Target HMS angle HMS momentum HMS collimator SHMS angle SHMS momentum SHMS collimator Time
LH2 18.5 deg -6.693 pion 8.5 deg -9.430 Collimator 30 min
LH2 18.5 deg -6.693 Pion 8.5 deg -7.3 Collimator 30 min
1.5% carbon 18.5 deg -5.816 Sieve 8.5 deg -7.3 Centered Sieve 1 hr
LH2 18.5 deg -5.816 Pion 16.5 deg -7.234 Collimator 1 hr
LH2 18.5 deg -5.816 Pion 16.5 deg -5.5 Collimator 1 hr
1.5% carbon 18.5 deg -5.816 Sieve 16.5 deg -5.5 Centered Sieve 2 hr

BCM Calibration ( 1 hour)

Use GEM to check out SHMS optics

  • Experts: Latif
  • Expected time:
  • Goal:
  • Conditions:
beam current: <1 μA
fast raster: off
target: optics targets
SHMS collimator: Collimator
SHMS trigger: 3/4 Scin + Cer
SHMS angle/momentum 25. deg, -2.0 GeV/c
  • Run Plan: