= Hall C Status =
 
= Hall C Status =
 
# Production
 
# Production
# Hall Work tomorrow: aerogel change (Vladimir), target training (Greg), change to 5-pass (accelerator)
 
  
 
= Current Run Plan =
 
= Current Run Plan =
Line 22: Line 21:
  
 
= Special Requests =
 
= Special Requests =
 +
# Hall Work tomorrow:
 +
## aerogel change (Vladimir)
 +
## target training (Greg)
 +
## change to 5-pass (accelerator)
  
 
= Useful Links =
 
= Useful Links =

Revision as of 16:53, 8 November 2021

RC Meeting Information

RC Daily Meetings are at 10 am, remote connection link: https://bluejeans.com/861439920 There is a 10:00 RC meeting today, 11/03/2021!

Accelerator Status

  1. Running beam to C and D (not sharing slit until after pass change)

Hall C Status

  1. Production

Current Run Plan

  1. 3-pass physics run plan: production, elastic singles, delta scan

Current Issues

  1. Replace flow switches for (HMS?) magnet power supplies: next opportunistic access (Joe Beaufait) ( PENDING )
  2. HMS Q3 insulating vacuum spikes generating annoyance alarms that take minutes to recover. https://logbooks.jlab.org/entry/3930175 Noise levels on transducers look OK, but Junaid's plot indicates Q3 is burping: https://logbooks.jlab.org/entry/3932992 .
  3. Serious HB LHe low liquid level alarms. https://logbooks.jlab.org/entry/3933051 Always seems to start with a subtle, simultaneous increase in level in Q1/2/3. https://logbooks.jlab.org/entry/3929152 .
  4. Target ladder camera was identified to be bad: Joe Beaufait will order camera ( PENDING )
  5. Still running with no UPS on the SHMS cryo controls - Heidi replaced, but need to check charge https://logbooks.jlab.org/entry/3937512
  6. HCCAM02 not functioning (lift required to replace-Brad is tracking this replacement).

Special Requests

  1. Hall Work tomorrow:
    1. aerogel change (Vladimir)
    2. target training (Greg)
    3. change to 5-pass (accelerator)