Initial conditions
- HMS/SHMS angle surveys.
- Beamline BPM and Harp surveys. Check offsets in MCC database.
- HMS/SHMS Conditions:
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
25 deg, -1.6 GeV/c
|
SHMS angle/momentum |
25 deg, -1.6 GeV/c
|
- Run 2.2 GeV beam four 4 days and switch to 3 pass.
- Run 6.4 GeV beam and switch to 5 pass.
- Run 10.6 GeV beam.
Completed
Center beam on C-hole target
- Experts:
- Expected time: 1 hour
- Goal: Center beam on carbon hole target
- Conditions:
beam current: |
5 μA
|
fast raster: |
3x3mm
|
target: |
carbon hole
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
25 deg, -1.6 GeV/c
|
SHMS angle/momentum |
25 deg, -1.6 GeV/c
|
Initial HMS/SHMS Detector Checkout
- SHMS/HMS optics experts:
- HMS DC experts:
- Expected time: 1 hour
- Goal: Initial checkout of the HMS/SHMS detectors. Working well enough for carbon elastics data and initial checkout of the SHMS/HMS tunes.
- Conditions:
beam current: |
5-20 μA
|
fast raster: |
off
|
target: |
0.5% carbon
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4,SCIN 3/4
|
HMS angle/momentum |
25 deg, -1.6 GeV/c
|
SHMS angle/momentum |
25 deg, -1.6 GeV/c
|
Wire Chamber
- SHMS Run plan:
- HMS Run plan:
Shower Counter
Scintillator
- SHMS Run plan:
- HMS Run plan:
Cerenkov
- SHMS Heavy Gas Cherenkov: Run Plan
- HMS Run plan:
Aerogel
Initial checkout of SHMS/HMS tune
- Experts: M Jones, H. Szumila
- Expected time: 1 hour
- Goal: Check tune with sieve
- Conditions:
beam current: |
5-20 μA
|
fast raster: |
off
|
target: |
0.5% carbon
|
HMS/SHMS collimator: |
SIEVE , CENTERED SIEVE
|
HMS/SHMS trigger: |
SCIN 3/4,SCIN 3/4
|
HMS angle/momentum |
25 deg, -1.6 GeV/c
|
SHMS angle/momentum |
25 deg, -1.6 GeV/c
|
Beam Energy Measurement
- Experts: MCC,Mark Jones, Dave Mack
- Expected time: 2 hours
- Goal: Measure beam energy for carbon elastics.
- Conditions:
beam current: |
5uA
|
fast raster: |
off
|
target: |
none
|
HMS delta scan with LH2
- Expected time: 5 hour
- Goal: Checkout HMS delta matrix. Have baseline for comparison at higher HMS central momentum
- Conditions:
beam current: |
3 μA
|
fast raster: |
1x1cm
|
target: |
10cm LH2
|
HMS collimator: |
Pion
|
HMS trigger: |
SCIN 3/4
|
HMS angle/momentum |
13.5 deg, -2.309 to -1.889 GeV/c
|
Inelastic on 1H at 21.95 degrees
- Experts: S. Malace
- Expected Time: 4 hour
- Goal : Data to compare to known cross sections
- Conditions: Prescale to 2 kHz
beam current (uA): |
5
|
fast raster: |
3x3
|
target: |
10cm LH2, 10cm aluminum
|
HMS collimator: |
PION
|
HMS trigger: |
SCIN 3/4
|
HMS angle/momentum |
21.95 / given in table
|
Eprime suggested time (Hydrogen) suggested time (10 cm Aluminum dummy)
1.6162 20 min 10 min
- Do target boiling and BCM calibration plans listed below. Then continue with the program
Eprime suggested time (Hydrogen) suggested time (10 cm Aluminum dummy)
1.3773 20 min 10 min
1.2000 20 min 10 min
1.0500 20 min 10 min
0.9000 20 min 10 min
Target boiling study
- Experts: Eric Christy
- Expected time: 1.5 hours
- Goal: Measure target boiling.
- Conditions: Prescale to 2 kHz, cycle magnets. Each current a ten minute run.
beam current (uA): |
1, 3, 5, 7, 10, 12, 15, 17, 20
|
fast raster: |
3x3mm
|
target: |
10cm LH2, 0.5% Carbon
|
HMS collimator: |
PION
|
HMS trigger: |
SCIN 3/4
|
HMS angle/momentum |
21.95 deg, -1.6162 GeV/c
|
BCM Calibration
- Experts: Eric Christy
- Expected time: 1 hour
- Goal: BCM Calibration data including low currents to look at non-linearities
- Conditions: Slit closed for zero current
- Procedure: Ask MCC to ramp up and then down covering the currents below with alternating on/off and 2 minutes at each current
beam currents (uA): |
0, 1, 0, 3, 0, 5, 0, 7, 0, 10, 0, 12, 0, 15, 0, 17, 0, 20
|
fast raster: |
off
|
target: |
0.5% Carbon
|
HMS angle |
21.95
|
HMS momentum |
1.2
|
Inelastic on 1H at 42.5 degrees
- Experts: S. Malace
- Expected Time: 9 hours
- Goal : Data to compare to known cross sections. Carbon target for pointing at the first momentum.
- Conditions: Prescale to 2 kHz
beam current (uA): |
10
|
fast raster: |
3x3
|
target: |
10cm LH2, 10cm dummy, 0.5% carbon
|
HMS collimator: |
PION
|
HMS trigger: |
SCIN 3/4
|
HMS angle/momentum |
42.5 / given in table
|
Eprime suggested time (Hydrogen) suggested time (10 cm Aluminum dummy) Carbon
1.2000 1 h 10 min 10 min
1.0400 1 h 10 min
0.9200 1 h 10 min
0.8000 1 h 10 min
0.7000 1 h 10 min
0.6000 1 h 10 min
SHMS Delta checkout with Carbon Elastic ground state
- Experts: M. Jones, H. Smuzila
- Expected time: 3 hour
- Goal: To take data with carbon elastic ground state and first excited state to test delta resolution.
- Conditions:
beam current: |
5-20 μA
|
fast raster: |
off
|
target: |
0.5% carbon
|
SHMS collimator: |
CENTERED SIEVE
|
SHMS trigger: |
SCIN 3/4
|
SHMS angle/momentum |
7.5 deg, 2.214 GeV/c
|
HMS Trigger Efficiency study
- Experts: E. Pooser
- Expected Time:
- Goal : To test sensitivity to threshold in the 3/4 and other triggers.
- Need to gain match the HMS Cerenkov according to Hamlet's suggestion elog entry
- Conditions: Parasitic with the HMS Angle/Position Optics Matrix
- Run Plan:
SHMS/HMS Delta Matrix calibration
- Experts: M. Jones, H. Smuzila
- Expected time: 12 hour
- Goal: To
- Conditions:
beam current: |
5-10 μA (whatever is stable)
|
fast raster: |
off
|
target: |
0.5% carbon
|
SHMS collimator: |
Collimator
|
SHMS trigger: |
SCIN 3/4
|
SHMS angle/momentum |
7.5 deg, various momentum
|
- Run Plan: Scan delta in 2% steps.
- Try with different vertical and horizontal beam positions.
SHMS Quartz bar gain matching
- Experts: S. Malace
- Expected Time: 1 hour
- Goal : Gain match quartz bars.
- Conditions:
beam current: |
5-10 uA (or more if easily available)
|
fast raster: |
3x3
|
target: |
10 cm LH2
|
SHMS |
Collimator
|
SHMS trigger: |
3/4 scin
|
SHMS angle/momentum |
25. deg, -1.4 GeV/c
|
HMS Angle and position matrix optimization for large ytgt (partially completed)
- Experts: M Jones, H Szumila
- Expected time:
- Goal: Calibrate HMS ytgt, yptar and xptar for 10cm target.
- Conditions:
beam current: |
10 uA (or more if easily available)
|
fast raster: |
off
|
target: |
Optics #1 target (0,+/-10cm foils) and Optics #2 target (+/-5cm foils)
|
HMS |
Sieve
|
HMS trigger: |
3/4 scin
|
HMS angle/momentum |
30. deg, -1.3 GeV/c
|
- Run Plan:
- Cycle magnets. Insert sieve.
- MCC will ask for ion chamber calibration on optics #1 and optics #2 target.
- Insert optics #1 target. Take data for 1 hour.
- Insert optics #2 target. Take data for 1 hour.
1H(eep) Coincidence SHMS (proton) and HMS (electron)
- Experts: D. Dutta, S. Basnet, A. Karki
- Expected time: 1 hour
- Goal: Setup coincidence timimg. Kinematic for HEEPcheck. Measure cross section.
- Conditions:
beam current: |
5-60 μA
|
fast raster: |
3x3mm
|
target: |
10cm LH2, 10cm dummy
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
65.1 deg, -0.936 GeV/c
|
SHMS angle/momentum |
25.0 deg, +2.012 GeV/c
|
1H(eep) Coincidence SHMS (electron) and HMS (proton)
- Experts: D. Dutta, S. Basnet, A. Karki
- Expected time: 1 hour
- Goal: Setup coincidence timimg. Kinematic for HEEPcheck. Measure cross section.
- Setting 1:
beam current: |
5-10 μA
|
fast raster: |
3x3mm
|
target: |
10cm LH2, 10cm dummy
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
53.3 deg, +0.957 GeV/c
|
SHMS angle/momentum |
25.0 deg, -1.816 GeV/c
|
- Setting 2: Here, we will do a mini-delta-scan in the SHMS to check acceptance.
beam current: |
5-10 μA
|
fast raster: |
3x3mm
|
target: |
10cm LH2, 10cm dummy
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
47.9 deg, +1.136 GeV/c
|
SHMS angle/momentum (a) |
30.0 deg, -1.816 GeV/c (-7%)
|
SHMS angle/momentum (b) |
30.0 deg, -1.686 GeV/c (0%)
|
SHMS angle/momentum (c) |
30.0 deg, -1.555 GeV/c (8.5)%
|
SHMS Angle and Position Matrix Optimization
- Experts:
- Expected time: 2 hour
- Goal: SHMS angle and position matrix optimization
- Conditions:
beam current: |
5-20 μA
|
fast raster: |
off
|
target: |
optics target 1, optics target 2
|
HMS/SHMS collimator: |
Sieve , Centered Sieve
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
30. deg, -1.3 GeV/c
|
SHMS angle/momentum |
25 deg, -1.4 GeV/c
|