RC Meeting and Runplan, Monday, August 27
From HallCWiki
Jump to navigationJump to search- Status
- Optics work Sunday did not completely converge - revisit today
- Initial, rough SHMS steering test Sunday SWING/Monday OWL
- IHA3H07A - looks like encoder readback issue (cable). Access Tuesday to fix
- Run plan
- Monday SWING, Tuesday OWL and DAY
- Beam optics tuning
- Big BPM calibration/checkout test plan
- After initial setup - SHMS steering plan will be executed (please call RC if not already on site). When MCC asks, ramp up magnets (one at a time) to settings for -8.5 GeV.
- Beam checkout
- For the following, see detailed run plan here: [1]
- Detector and trigger checkout. Call experts before start (after hole-target is centered): Malace, Pooser, Berdnikov, Ambrose for detector checkout, Malace, Poose, Huber, Trotta for trigger checkout
- Calibration runs
- RF recovery scheduled for Tuesday - Hall C going to Controlled Access until ~ 1 pm
- Controlled Access tasks
- Harp repair
- Walk -throughs
- SHMS PMT investigation
- Monday SWING, Tuesday OWL and DAY