Hall C Weekly Meeting - April 7, 2014

From HallCWiki
Jump to navigationJump to search
  • Walter Kellner
    • The Anaconda is ready to be lifted with a rented crane this week
    • Techs are working on supports for the Compton chicane magnets
  • Mike Fowler
    • Contracts for which he was SOTR are done
    • Will be working on magnet/rotation controls for the SHMS. Asking for comments on GUI screen design. Here are the current HMS Controls screens as a reference.
    • Q: Should the collimator/slit controls for the SHMS (and HMS) be integrated into the magnet/rotation controls?
  • Joe Beaufait
    • Is taking SOTR training
    • Did a Hall A power walk down as part of planning for SBS power
    • A rough layout for SHMS auxilliary circuits is done. The work and materials are going out for bids.
  • Paul Brindza
    • The HB and Q1 vendors are continuing to weld shut LHE vessels.
    • The first SHMS dipole double pancake winding is done
    • Insulation is being done this week and vacuum impregnation next week
    • Dipole first double pancake winding done.
    • The mandrel on winding station two is being tested for vacuum tightness this week
    • Design work:
      • Working out rigging plan for SHMS magnet assembly
      • Design of SHMS HVAC is complete
      • Design of SHMS lead glass shield wall and retainer is complete
      • Details are being worked out on the SHMS angle floor plates
  • Steve Wood
    • Hall A and C will hold a joint physics meeting June 5 & 6