RC Meeting and Runplan, Wednesday, August 29
From HallCWiki
Jump to navigationJump to search- Status
- Reasonable spot size achieved at 3H07A and B harps yesterday evening, early OWL shift.
- From that point - worked on sending CW to Hall C. Dealing with BLMs issues, etc. in machine.
- Dave M. takes over as RC.
- Runplan
- Wednesday SWING, Tuesday OWL and DAY
- Beam optics tuning
- Big BPM calibration/checkout test plan
- After initial setup - SHMS steering plan will be executed (please call RC if not already on site). When MCC asks, ramp up magnets (one at a time) to settings for -8.5 GeV.
- Beam checkout
- For the following, see detailed run plan here: [1]
- Detector and trigger checkout. Call experts before start (after hole-target is centered): Malace, Pooser, Berdnikov, Ambrose for detector checkout, Sawatzky, Malace, Pooser, Huber, Trotta for trigger checkout)
- Calibration runs
- Note: Dave G. is seeing some odd results when comparing the BPMs and harps using scans from OWL shift Aug. 29. It would be useful to do a quick BPM/harp calibration in the near future if there's time.
- Wednesday SWING, Tuesday OWL and DAY