Beam energy of 6.4 GeV
Initial conditions
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
15 deg, -3.0 GeV/c
|
SHMS angle/momentum |
15 deg, -3.0 GeV/c
|
Beam Checkout with Superharps and Beam Position Monitors (3 hours)
- Experts: Mark Jones, Deb Biswas, Thir Guatam
- Expected time: 3 hours
- Goals: Initial measurement of beam spot size. Followed by calibration of girder BPMs at 5,30 and 60uA. Measure raster size with superharps.
- Conditions:
beam current: |
5,30 and 60 μA
|
fast raster: |
off
|
target: |
none
|
- Runplan: pdf file
- Ask MCC to do superharp scan with superharps IHA3H07A and IHA3H07B and put entry in ELOG. Record the 3 BPMs positions (3H07A,3H07B,3H07C) during scan.
- Want beam spot with sigma_x and sigma_y below 200 um ( beam pass 1-4) and below 300 um for beam pass 5.
- Verify Girder BPM position to Harp positions.
Center beam on C-hole target ( 1 hour)
- Experts:
- Expected time: 1 hour
- Goal: Center beam on carbon hole target
- Conditions:
beam current: |
5 μA
|
fast raster: |
3x3mm
|
target: |
carbon hole
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
15 deg, -3.0 GeV/c
|
SHMS angle/momentum |
15 deg, -3.0 GeV/c
|
- Run plan: Procedure
- Once hole is found, take 20 minutes run at 20uA for good statistics
Detailed Detector Checkout ( 2 hour)
- Experts:
- Expected time: 2 hour
- Prerequisite: Eric Pooser will do invasive checkout of HMS/SHMS trigger with beam.
- Conditions:
beam current: |
20 μA
|
fast raster: |
off
|
target: |
0.5% carbon
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4,SCIN 3/4
|
HMS angle/momentum |
15 deg, -3.0 GeV/c
|
SHMS angle/momentum |
15 deg, -3.0 GeV/c
|
Trigger
- Set HMS/SHMS trigger threshold for PID trigger section to 10 mV.
- Software cuts can be placed on trigger ADC data to study efficiencies.
Cerenkov
- SHMS Noble Gas Run Plan: Scan of HV ( Eric Pooser)
Run 1 HV Settings: PMT1 = 2200 V, PMT2 = 2230 V, PMT3 = 2115, PMT4 = 2030
Run 2 HV Settings: PMT1 = 2300 V, PMT2 = 2320 V, PMT3 = 2215, PMT4 = 2130
- These are the spring 2017 KPP HV settings for reference: NGC1 : 2255 V, NGC2 : 2280 V, NGC3 : 2165 V, NGC4 : 2087 V
- We will also need to check the NGCER sum the PID trigger circuit to ensure that we are not saturating the FADC channel
- Run plan (series of 15 minutes runs)
Run |
HMS DAQ |
SHMS DAQ |
Comments
|
1 |
No data taking |
Only 3/4 scin trigger |
Checkout of HMS 3/4 trigger ; SHMS NGC HV NGC1 : 2255 V, NGC2 : 2280 V, NGC3 : 2165 V, NGC4 : 2087 V
|
2 |
Only 3/4 scin trigger |
No data taking |
Checkout of SHMS 3/4 trigger
|
3 |
Only 3/4 scin trigger |
Only 3/4 scin trigger |
Checkout of HMS ELCLEAN/ELREAL trigger; SHMS NGC HV PMT1 = 2200 V, PMT2 = 2230 V, PMT3 = 2115, PMT4 = 2030
|
4 |
Only 3/4 scin trigger |
Only 3/4 scin trigger |
Checkout of HMS ELCLEAN/ELREAL trigger ; SHMS NGC HV PMT1 = 2300 V, PMT2 = 2320 V, PMT3 = 2215, PMT4 = 2130
|
5 |
Only ELCLEAN trigger |
Only 3/4 scin trigger |
Checkout of SHMS ELCLEAN/ELREAL trigger
|
6 |
Only ELREAL trigger |
Only 3/4 scin trigger |
Checkout of SHMS ELCLEAN/ELREAL trigger
|
7 |
ELREAL trigger, prescale 3/4 SCIN |
Only ELCLEAN |
|
8 |
ELCLEAN trigger, prescale 3/4 SCIN |
Only ELREAL |
|
9 |
ELCLEAN trigger, different prescale 3/4 SCIN |
ELREAL, prescale 3/4 scin |
|
Checkout of SHMS/HMS focal plane tune ( 1 hour)
- Experts:
- Expected time: 1 hour
- Goal: Look at focal plane with sieve to check tune
- Conditions:
beam current: |
20 μA
|
fast raster: |
off
|
target: |
0.5% carbon
|
HMS/SHMS collimator: |
SIEVE , Centered sieve
|
HMS/SHMS trigger: |
SCIN 3/4,SCIN 3/4
|
HMS angle/momentum |
15 deg, -3.0 GeV/c
|
SHMS angle/momentum |
15 deg, -3.0 GeV/c
|
Different Pi/e ratios ( 1.5 hour)
- Experts: SImona
- Expected time: 1.5 hr
- Goal:
- Runs with different central momentum and different pi/e ratios.
- Two runs with LH2 and one with LD2
- Take each setting with only 3/4 scin trigger and for 30 minutes
- Set PID tirgger thresholds to 10 mV. Offline will determine thresholds to test later.
- Conditions:
beam current: |
5-20 μA
|
fast raster: |
2x2mm
|
target: |
10cm LH2, 10cm LD2
|
HMS/SHMS collimator: |
Pion/Collimator
|
HMS/SHMS trigger: |
SCIN 3/4 / SCIN 3/4
|
SHMS/HMS angle/momentum |
25. deg, -3.0 GeV/c, -1.4
|
HMS angle/mom |
SHMS angle/mom |
Target |
HMS/SHMS Trigger
|
25./-3.0 |
25./-3.0 |
10cm LH2 |
Only 3/4 scin
|
25./-1.4 |
25./-1.4 |
10cm LH2 |
Only 3/4 scin
|
25./-1.4 |
25./-1.4 |
10cm LD2 |
Only 3/4 scin
|
Defocused Tune for SHMS/HMS ( 1 hour)
- Experts: Hamlet
- Expected time: 1 hr
- Goal: Have a wider y_fp to calibrate the calorimeter over regions that are not usually hit with the standard hourglass tune.
- Conditions:
beam current: |
5-20 μA
|
fast raster: |
2x2mm
|
target: |
10cm LH2
|
HMS/SHMS collimator: |
Pion/Collimator
|
HMS/SHMS trigger: |
SCIN 3/4 / SCIN 3/4
|
SHMS/HMS angle/momentum |
25. deg, -3.0 GeV/c, Q2 at 1.2 times normal
|
Elastic p(ep) Checkout Small angle (2 hours)
- Experts:
- Expected time:
- Goal:
- Conditions:
beam current: |
10 μA
|
fast raster: |
1x1mm2
|
target: |
10cm LH2
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
13.5/16. deg / 5.398/5.074 GeV
|
SHMS angle/momentum |
8.,10.,13.5 deg / 6.017,5.814,5.398 GeV
|
HMS Angle/Mom |
HMS rate |
SHMS Angle/Mom |
SHMS rate |
Run time
|
13.5/5.398 |
300 |
8./6.017 |
3300 Hz |
15 minutes
|
13.5/5.398 |
300 |
10./5.817 |
1000 |
30 minutes
|
16.0/5.074 |
100 |
13.5/5.398 |
150 |
60 minutes
|
HMS/SHMS Angle and Position Matrix Optimization (5 hours)
- Experts:
- Expected time: 5 hours.
- Goal:
- Conditions:
beam current: |
20 μA ( more is better)
|
fast raster: |
off
|
target: |
optics targets
|
HMS/SHMS collimator: |
Sieve , Centered/Shifted Sieve
|
HMS/SHMS trigger: |
3/4 scin, 3/4 scin
|
HMS angle/momentum |
15 and 22. deg,
|
SHMS angle/momentum |
15. and 22. deg,
|
- Series of runs changing target.
- SHMS has two sieves with the holes shifted in the horizontal.
- HMS has only one sieve which will always be used.
- No raster.
- Time is assuming 20uA.
Target |
HMS angle |
HMS momentum |
SHMS angle |
SHMS momentum |
SHMS collimator |
Time
|
0,+/- 10cm |
15. deg |
-4.0 |
15. deg |
-4.0 |
Centered Sieve |
30 min
|
0,+/- 10cm |
15. deg |
-4.0 |
15. deg |
-4.0 |
Shifted Sieve |
30 min
|
+/- 5cm |
15. deg |
-4.0 |
15. deg |
-4.0 |
Centered Sieve |
30 min
|
+/- 5cm |
15. deg |
-4.0 |
15. deg |
-4.0 |
Shifted Sieve |
30 min
|
0,+/- 10cm |
22. deg |
-3.2 |
22. deg |
-3.2 |
Centered Sieve |
1.5 hr
|
0,+/- 10cm |
22. deg |
-3.2 |
22. deg |
-3.2 |
Shifted Sieve |
1.5 hr
|
Large Ytar: HMS/SHMS Angle and Position Matrix Optimization (9 hours)
- Experts:
- Expected time: 9 hours.
- Goal:
- Conditions:
beam current: |
20 μA
|
fast raster: |
off
|
target: |
optics targets
|
HMS/SHMS collimator: |
Sieve , Centered Sieve
|
HMS/SHMS trigger: |
3/4 scin, 3/4 scin
|
HMS angle/momentum |
30. deg, -2.0 GeV/c
|
SHMS angle/momentum |
30. deg, -2.0 GeV/c
|
Check of ELREAL/ELCLEAN Trigger ( 1.5 hour)
- Experts: SImona
- Expected time: 1.5 hr
- Goal:
- Use threshold determined form previous LD2 running
- Sanity check of electron triggers.
- Conditions:
beam current: |
20 μA
|
fast raster: |
2x2mm
|
target: |
10cm LH2
|
HMS/SHMS collimator: |
Pion/Collimator
|
HMS/SHMS trigger: |
Electron triggers
|
SHMS/HMS angle/momentum |
25. deg, -3.0 GeV/c, -1.4
|
HMS angle/mom |
SHMS angle/mom |
Target |
HMS/SHMS Trigger |
Total DAQ Triggers
|
25./-3.0 |
25./-3.0 |
10cm LH2 |
Only 3/4 scin (prescale trig1=0,trig2=-1,trig3=-1) |
300K
|
25./-3.0 |
25./-3.0 |
10cm LH2 |
ELREAL (prescale trig1=-1,trig2=0,trig3=-1) |
300K
|
25./-3.0 |
25./-3.0 |
10cm LH2 |
ELCLEAN (prescale trig1=-1,trig2=-1,trig3=0) |
300K
|
25./-1.4 |
25./-1.4 |
10cm LH2 |
Only 3/4 scin (prescale trig1=0,trig2=-1,trig3=-1) |
300K
|
25./-1.4 |
25./-1.4 |
10cm LH2 |
ELREAL (prescale trig1=-1,trig2=0,trig3=-1) |
300K
|
25./-1.4 |
25./-1.4 |
10cm LH2 |
ELCLEAN (prescale trig1=-1,trig2=-1,trig3=0) |
300K
|
Coincidence Checkout [9 hrs]
- Experts:
- Expected time:
- Goal:
- Conditions:
beam current: |
20-50 μA
|
fast raster: |
2x2 mm2
|
target: |
10cm LH2
|
HMS/SHMS collimator: |
PION/SIEVE , COLLIMATOR/CENTERED SIEVE
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
27.5 deg, -3.609 GeV/c
|
SHMS angle/momentum |
27.5 deg, +3.609 GeV/c
|
- Series of runs with/without collimator on electron side and switch polarities between HMS/SHMS.
- Last run is used to evaluate accidentals.
HMS angle |
HMS momentum |
SHMS angle |
HMS collimator |
SHMS momentum |
SHMS collimator |
Time
|
27.5 deg |
+3.609 |
27.5 deg |
Pion |
-3.609 |
Collimator |
30 min (4Hz at 20uA)
|
27.5 deg |
+3.609 |
27.5 deg |
Pion |
-3.609 |
Centered Sieve |
2 hr
|
27.5 deg |
-3.609 |
27.5 deg |
Pion |
+3.609 |
Collimator |
30 min (4Hz at 20uA)
|
27.5 deg |
-3.609 |
27.5 deg |
Sieve |
+3.609 |
Collimator |
2 hr
|
27.5 deg |
-3.609 |
35.0 deg |
Pion |
+3.609 |
Collimator |
1 hr
|
Additional Large Ytar: HMS/SHMS Angle and Position Matrix Optimization (6 hours)
- Experts:
- Expected time: 6 hours.
- Goal:
- Conditions:
beam current: |
65 μA
|
fast raster: |
2x2
|
target: |
optics targets
|
HMS/SHMS collimator: |
Sieve , Centered Sieve
|
HMS/SHMS trigger: |
3/4 scin, 3/4 scin
|
HMS angle/momentum |
25.5,22 deg, -2.6,-3.2 GeV/c
|
SHMS angle/momentum |
30.,22 deg, -2.0,-3.2 GeV/c
|
- Run Plan: Time is assuming 65uA. Take one hour long runs. Should take about 5 hours for +/-10cm data and 1 hour for +/-5cm data.
Target |
HMS angle |
HMS momentum |
SHMS angle |
SHMS momentum |
SHMS collimator |
Counts
|
0,+/- 10cm |
25. deg |
-2.6 |
30. deg |
-2.0 |
Centered Sieve |
Total of 4.0M SHMS triggers.
|
+/- 5cm |
22. deg |
-3.2 |
22. deg |
-3.2 |
Centered Sieve |
Total of 1.0M SHMS Triggers.
|
Additional Coincidence Checkout [1 hr]
beam current: |
65 μA
|
fast raster: |
2x2 mm2
|
target: |
10cm LH2
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
22.0 deg, -4.284 GeV/c
|
SHMS angle/momentum |
33.3 deg, +2.925 GeV/c
|
- Run Plan:
- HMS is detecting electrons and SHMS is detecting protons.
- Set trigger prescales to take only coincidence triggers.
- Expect coincidence rate around 65 Hz.
Beam Energy Measurement (3 hours)
- Experts: MCC, Jay Benesch
- Expected time: 3 hours
- Goal: Measure beam energy for elastics
- Conditions:
beam current: |
5uA
|
fast raster: |
off
|
target: |
none
|
CT Physics
Target LH2/LD2 boiling study
- Experts: Eric Christy, Simona Malace
- Expected time: ? hours
- Goal: Measure target boiling.
- Conditions: Prescale to 2 kHz, cycle magnets.
beam current (uA): |
2, 7, 10, 20, 30, 40, 50, 60, max current
|
fast raster: |
2x2mm
|
target: |
10cm LH2, 10cm LD2, 0.5% Carbon, *Al 10 cm Dummy only at 20 and 40 muA*
|
SHMS/HMS collimator: |
Collimator/PION
|
SHMS trigger: |
SCIN 3/4
|
SHMS angle/momentum: |
15 deg / -3 GeV/c
|
HMS trigger: |
SCIN 3/4
|
HMS angle/momentum: |
15 deg / -3 GeV/c
|
Use GEM to check out SHMS optics
- Experts:
- Expected time:
- Goal:
- Conditions:
beam current: |
<1 μA
|
fast raster: |
off
|
target: |
optics targets
|
SHMS collimator: |
Collimator
|
SHMS trigger: |
3/4 Scin + Cer
|
SHMS angle/momentum |
25. deg, -2.0 GeV/c
|
SHMS Elastic p(ep) Checkout Additional angles (4 hours)
- Experts:
- Expected time:
- Goal:
- Conditions:
beam current: |
65uA
|
fast raster: |
2x2mm2
|
target: |
0.5% carbon, 10cm LH2
|
SHMS collimator: |
PION , COLLIMATOR
|
SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
SHMS angle/momentum |
16,20 ,30,35 deg / 5.074,4.522,3.349,2.869 GeV
|
- Run plan
- Take 15 min run with 0.5% carbon. Run LH2 for 10,000 events in elastic W for SHMS at 16 deg.
- Take 15 min run with 0.5% carbon. Run for 10,000 events in elastic W for SHMS at 20 deg
- Take 15 min run with 0.5% carbon. Run for 10,000 events in elastic W for SHMS at 30 deg
- Take 15 min run with 0.5% carbon. Run for 10,000 events in elastic W for SHMS at 35 deg
Lower priority
BCM Calibration ( 1 hour)
- Have done a set of data. Need to analyze and confirm it is enough.
1H or 12C(e, e’ π) [2 hr]
- Experts:
- Expected time:
- Goal:
- Conditions:
beam current: |
20-50 μA
|
fast raster: |
1x1mm2
|
target: |
3% carbon, 10cm LH2
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
16.8 deg, -3.8 GeV/c
|
SHMS angle/momentum |
20.0 deg, +2.7 GeV/c
|
1H(e’K) and 1H(e, e’K) [3 hr]
- Experts:
- Expected time:
- Goal:
- Conditions:
beam current: |
20-50 μA
|
fast raster: |
1x1mm2
|
target: |
10cm LH2
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
25.0 deg, -2.6 GeV/c
|
SHMS angle/momentum |
15.0 deg, +3.6 GeV/c
|
Beam energy of 8.8 GeV
Beam Energy Measurement
- Experts: MCC,Mark Jones, Dave Mack
- Expected time: ? hours
- Goal: Measure beam energy for carbon elastics.
- Conditions:
beam current: |
5uA
|
fast raster: |
off
|
target: |
none
|
SHMS Tune Verification
- Experts:
- Expected time:
- Goal:
- Conditions:
beam current: |
5-20 μA
|
fast raster: |
off
|
target: |
3% carbon
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
|
SHMS angle/momentum |
|
1H(eep)
Beam energy of 10.6 GeV
Beam Energy Measurement
- Experts: MCC,Mark Jones, Dave Mack
- Expected time: ? hours
- Goal: Measure beam energy for carbon elastics.
- Conditions:
beam current: |
5uA
|
fast raster: |
off
|
target: |
none
|
1H(eep)
SHMS Tune Verification
- Experts:
- Expected time:
- Goal:
- Conditions:
beam current: |
5-20 μA
|
fast raster: |
off
|
target: |
3% carbon
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
SCIN 3/4, SCIN 3/4
|
HMS angle/momentum |
|
SHMS angle/momentum |
|