CT Experiment (E1206107) Run Plan
The 6.4 GeV Run Plan (52 hrs)
beam current: |
65 μA
|
fast raster: |
2x2 mm2
|
target: |
10cm LH2
|
HMS/SHMS collimator: |
PION , COLLIMATOR
|
HMS/SHMS trigger: |
Coincidence
|
HMS angle/momentum |
Various
|
SHMS angle/momentum |
Various
|
- Run Plan:
- HMS is detecting electrons and SHMS is detecting protons.
- Use HMS pion collimator and SHMS collimator.
- Start with 30uA on lower 6% Carbon, after a 2 hr run, increase to 40 uA and after another 2 hr run move to the upper 6% Carbon and ask for 50 uA.
- Keep track of good coincidence physics events (with tight PID cuts and coincidence time cut) such that we have 10000 events for LH2 and Carbon
Target |
Prescales |
HMS angle |
HMS momentum |
SHMS angle |
SHMS momentum |
Time |
Complete
|
LH2 |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
45.1 deg |
-2.131 |
17.1 deg |
+5.122 |
12 hrs |
Y
|
LH2 |
ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 |
45.1 deg |
-2.131 |
17.1 deg |
+5.122 |
30 min |
Y
|
Al. Dummy |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
45.1 deg |
-2.131 |
17.1 deg |
+5.122 |
4 hrs |
Y
|
6% C |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
45.1 deg |
-2.131 |
17.1 deg |
+5.122 |
36 hrs |
Y
|
6% C |
ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 |
45.1 deg |
-2.131 |
17.1 deg |
+5.122 |
30 min |
Y
|
The 10.6 GeV Run Plan (282 hrs)
beam current: |
65 μA
|
fast raster: |
2x2 mm2
|
target: |
10cm LH2
|
HMS/SHMS collimator: |
LARGE , COLLIMATOR
|
HMS/SHMS trigger: |
Coincidence
|
HMS angle/momentum |
Various
|
SHMS angle/momentum |
Various
|
- Run Plan:
- HMS is detecting electrons and SHMS is detecting protons.
- Use HMS pion collimator and SHMS collimator.
Target |
Prescales |
HMS angle |
HMS momentum |
SHMS angle |
SHMS momentum |
Time |
Complete
|
LH2 |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
23.2 deg |
-5.539 |
21.6 deg |
+5.925 |
4 hrs (3 Hz) |
Y
|
- Q^2 = 14.3 GeV^2 Run Plan
- Cycle SHMS magnets since raising momentum
- Keep track of good coincidence physics events (with tight PID cuts and coincidence time cut) such that we have 1000 events each for LH2 and Carbon and take two singles run 30 mins each at the beginning and end of the running on a particular target.
- For the singles runs the prescale factor on SHMS should be adjusted as needed to get about equal rate in HMS and SHMS (ie equal rates for PS1 and PS4).
Target |
Prescales |
HMS angle |
HMS momentum |
SHMS angle |
SHMS momentum |
Time |
Complete
|
LH2 |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
39.3 deg |
-2.982 |
12.8 deg |
+8.505 |
36 hrs |
Y
|
LH2 |
ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 |
39.3 deg |
-2.982 |
12.8 deg |
+8.505 |
1 hr |
Y
|
Al. Dummy |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
39.3 deg |
-2.982 |
12.8 deg |
+8.505 |
3 hrs |
Y
|
6% C |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
39.3 deg |
-2.982 |
12.8 deg |
+8.505 |
122 hrs |
Y
|
6% C |
ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 |
39.3 deg |
-2.982 |
12.8 deg |
+8.505 |
1 hr |
Y
|
- Q^2 = 11.5 GeV^2 Run Plan
- Cycle HMS magnets since raising momentum
- Keep track of good coincidence physics events (with tight PID cuts and coincidence time cut) such that we have 1000 events each for LH2 and Carbon
- For the singles runs the prescale factor on SHMS should be adjusted as needed to get about equal rate in HMS and SHMS (ie equal rates for PS1 and PS4).
Target , current |
Prescales |
HMS angle |
HMS momentum |
SHMS angle |
SHMS momentum |
Time |
Complete
|
6% C, 50uA |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
28.5 deg |
-4.478 |
17.8 deg |
+7.001 |
18.5 hrs |
In progress
|
6% C, 50 uA |
ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 |
28.5 deg |
-4.478 |
17.8 deg |
+7.001 |
30 min |
Y
|
LH2, 65 uA |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
28.5 deg |
-4.478 |
17.8 deg |
+7.001 |
3.5 hrs |
Y
|
LH2, 65 uA |
ps1=0,ps2=-1,ps3=-1,ps4=0,ps5=-1,ps6=-1 |
28.5 deg |
-4.478 |
17.8 deg |
+7.001 |
30 min |
Y
|
Al. Dummy, max allowed |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
28.5 deg |
-4.478 |
17.8 deg |
+7.001 |
1 hrs |
Y
|
- Q^2 = 10.0 GeV^2 Run Plan for checking radiative corrections.
- Cycle HMS magnets since raising momentum
- Keep track of good coincidence physics events (with tight PID cuts and coincidence time cut) such that we have 800 events on 1.5% Carbon
Target |
Prescales |
HMS angle |
HMS momentum |
SHMS angle |
SHMS momentum |
Time |
Complete
|
1.5% C |
ps1=-1,ps2=-1,ps3=-1,ps4=-1,ps5=-1,ps6=0 |
24.5 deg |
-5.259 |
20.6 deg |
+6.209 |
12 hrs |
N
|
F2 Experiment (E12-10-002) L/T measurement Run Plan
- Experts: Simona Malace, Eric Christy
- Expected time: 2 days at 30 muA
- Goal: Measure one epsilon point to better constrain R at large x
- Conditions: ONLY HMS NEEDED. Prescale to 2 kHz, cycle magnets.
beam current (uA): |
max current
|
fast raster: |
2x2mm
|
target: |
10 cm LH2, Al 10 cm Dummy
|
HMS collimator: |
PION
|
HMS trigger: |
ELREAL for physics data taking
|
HMS trigger: |
SCIN 3/4 *for one run only* in the beginning for trigger efficiency calculation (we are running one trigger at the time)
|
HMS angle/momentum: |
65 deg / -1 GeV/c - 100 K electrons
|
HMS angle/momentum: |
65 deg / +1 GeV/c - 10 K positrons
|
F2/EMC Experiment (E12-10-002/E12-10-008) 5 pass Run Plan
- Spokespeople E12-10-002: E. Christy, T. Keppel, S. Malace (contact), I. Niculescu
- Graduate Students E12-10-002: Deb Biswas, Abel Sun, Fernando Araiza Gonzalez
- Spokespeople E12-10-008: J. Arrington, A. Daniel, D. Gaskell (contact), N. Fomin
- Graduate Students E12-10-008: Abishek Karki, Kayla Craycraft
beam current: |
varies per target
|
fast raster: |
2x2 mm2
|
targets: |
10cm LH2 and LD2, 10 cm Al Dummy, Be, 10,11B, C 1.5 %
|
HMS/SHMS collimator: |
Large , COLLIMATOR
|
HMS/SHMS trigger: |
ELREAL/ELREAL for NEG. Polarity runs; ELCLEAN/ELCLEAN for POS. Polarity runs
|
HMS angle/momentum |
Various (check run plan below)
|
SHMS angle/momentum |
Various (check run plan below)
|
HMS Dipole saturation check run plan (3-4 hrs):
- Perform HMS e-p elastic checks at 21 degrees and use position of elastic peak to check for dipole saturation for 2 momenta.
- SHMS will be set at 21 degrees and a central momentum of -5.7 GeV for the entire study
- Both HMS and SHMS detecting electrons.
- Use HMS pion collimator and SHMS collimator.
- All runs take with ps1 = 0, ps2 = ps3 = ps4 = ps5 = ps6 = -1
beam current: |
60 μA or maximum available
|
fast raster: |
2x2 mm2
|
targets: |
10cm LH2, 10cm dummy
|
HMS/SHMS collimator: |
PION, COLLIMATOR
|
HMS/SHMS trigger: |
singles
|
Target |
HMS angle |
HMS momentum |
Time
|
LH2 |
21.00 deg |
-6.1 |
1 hr
|
10cm Dummy |
21.00 deg |
-6.1 |
20 min
|
LH2 |
21.00 deg |
-5.9 |
1 hr
|
10cm Dummy |
21.00 deg |
-5.9 |
20 min
|
SHMS Production Run Plan
HMS Production Run Plan
- Online Analysis Flow: shift takers! follow closely, please
F2/EMC analysis how-to for shift takers
Daily to do list
Deuteron Electro-Disintegration (E12-10-003) Run Plan
- Experts: Werner Boeglin, Mark Jones
- Graduate Student: Carlos Yero
- Expected Time: 6 days at 70 uA
- Goal: Measure D(e,e'p)n cross section at three kinematic settings, where FSI are small
- Conditions: The SHMS will detect electrons and the HMS will detect protons.
beam energy: |
10.6 GeV
|
beam current: |
40 μA
|
fast raster: |
2x2 mm
|
targets: |
10cm LH2, 10cm LD2
|
HMS/SHMS collimator: |
Pion , Collimator
|
HMS/SHMS trigger: |
Coincidence, HMS: h3/4, SHMS: p3/4
|
HMS angle/momentum |
Various
|
SHMS angle/momentum |
Fixed
|
- H(e,e'p) Check Run Plan
- Check the HMS/SHMS spectrometer pointing
Target |
SHMS angle |
SHMS momentum |
HMS angle |
HMS momentum |
Time
|
LH2 |
12.169 deg |
-8.70 GeV/c |
37.339 deg |
+2.938 GeV/c |
1 hr
|
- D(e,e'p)n Run Plan
- Calibration run at low missing momentum used as a cross check with existing data
- Measure the D(e,e'p)n Cross Section at unexplored high missing momentum kinematics settings
Target |
SHMS angle |
SHMS momentum |
HMS angle |
HMS momentum |
Missing Momentum |
Time
|
LD2 |
12.169 deg |
-8.70 GeV/c |
38.896 deg |
+2.932 GeV/c |
80 MeV |
1 hr
|
Alternative Run Plan (Assuming Beam Current of 65-70 uA)
- The initial H(e,e'p) checkout and D(e,e'p)n at low missing momentum is the SAME as above.
LD2 |
12.169 deg |
-8.70 GeV/c |
53.252 deg |
+2.305 GeV/c |
500 MeV |
8 hrs
|
LD2 |
12.169 deg |
-8.70 GeV/c |
56.401 deg |
+2.220 GeV/c |
650 MeV |
18 hrs
|
LD2 |
12.169 deg |
-8.70 GeV/c |
59.388 deg |
+2.120 GeV/c |
800 MeV |
36 hrs
|
Fall 2017 Commissioning Plans
Spring 2017 KPP run
Hall C Links
Hall C
Hall C is one of four experimental halls at JLab.
Hall C Computing.
Hall C in the Press.
Basic Equipment in Hall C
Beamline
SHMS Magnets
For the Fall 2017 run, see intructions at https://hallcweb.jlab.org/wiki/index.php/How-to
The formulas and program should be kept in sync with the repository.
- Formulas used for setting current of SHMS magnets during KPP
Magnet |
Formula
|
HB |
Current = 330.05*p - 3.1784*p^2 + 0.4018*p^3
|
Q1 |
Current = 222.4*p - 7.709*p^2 + 0.6684*p^3
|
Q2 |
Current = 3661*p/11
|
Q3 |
Current = 2434*p/11
|
Dipole |
Current = 3450*p/11
|
Scattering Chamber
- The scattering chamber window on the SHMS side is 0.020 inches thick 2024-T4 aluminum.
SHMS Entrance Window and Vacuum vessel
- The Horizontal Bender entrance window is 0.010 inches thick 2024-T3 aluminum.
- The dipole exit window is 0.020 inches thick 5056 aluminum.
Target
Spring 2017 KKP run
Fall 2017 run
- Logbook entry on the Fall target configuration which has links to file describing the targets and their thicknesses and a file with the mechanical drawing of the target ladder.
- BeO target was replaced by the "halo" cylinder target. Logbook entry with drawing of "halo" cylinder target.
- Drawing of target ladder with cryo cells and solid target ladder.
- Drawing of cryotarget cell with 2.5inch diameter and 10 cm long (after using insert entrance window). Used for separate LH2 and LD2 cells in ladder.
- Drawing of cryotarget with 1.6 inch diameter for 4cm cell.
- Drawing of cryotarget with 1.6 inch diameter for 10cm cell.
HMS Magnets and Vacuum Vessel
HMS Detectors
SHMS Detectors
DAQ & Trigger
Controls
- High Voltage
- Spectrometer Controls (Use go_cmagnets command)
- HMS and SHMS Collimator Control document.
Online Replay
Data Analysis
Monte Carlo
Hall C at 12 GeV